Page 190 - Civil Engineering Project Management, Fourth Edition
P. 190

171
                                                              Programme and progress charts
                          does not give a false impression of progress the following adjustments are
                          advisable:
                          • The ‘target’ cost should include the contingency money provided. A lower
                             line at the base of the graph can show this contingency money and the
                             expenditure against it, thus revealing where any exceedance of the target
                             is due to excess contingency money spent.
                          • If there is a major item of expenditure incurred late in the contract (such as for
                             supply and installation of plant), the value of this should also be excluded,
                             or be plotted separately as an additional line.
                          • The cumulative valuations plotted monthly should not include retention
                             money deducted, nor payment on account for materials on site, nor reim-
                             bursement of increased costs of wages and prices.
                          Although such a progress chart is not exact, it is a good indicator of progress.
                          Usually the plot of valuations forms an S-curve, having its steepest inclination
                          during the central part of the contract period when productivity should be
                          at its greatest. As a consequence, if the plotted line of valuations does not rise
                          above the straight line sometime during the middle period of the contract, then
                          almost certainly the contract will finish late.
                            One advantage of a progress chart of this kind is that, when an employer
                          needs an estimate of future rates of expenditure, this can be estimated by
                          sketching in an S-curve of the type shown and reading off the monthly rates
                          of expenditure it implies, less any retention money held back.
                            Some standard conditions of contract, such as those of FIDIC (see Section 4.3)
                          require the contractor to produce a cash-flow forecast along with his programme
                          for construction. It must be remembered, however, that a cash-flow from interim
                          payments does not necessarily represent construction progress, because deduc-
                          tions are made for retention and additions may be made for advance payments
                          (if any), and materials delivered to site.
                            Similar types of cumulative output chart can be applied to specific types of
                          work. One for concrete work to different structures is shown in Fig. 14.4. The
                          horizontal bands show to scale the amount of concrete to be placed in each
                          structure. The cumulative amount of concrete placed month by month can be
                          plotted for each structure, and their total shown separately. Such a chart is
                          useful for indicating where slow progress is occurring.
                            For a mainlaying contract the type of progress chart shown in Fig. 14.5 can
                          be used. It is self-explanatory. The profile of the main may have to be shown
                          in a condensed form; it also shows where specials are required.



                          14.5 Network diagrams and critical path planning


                          A network ‘diagram’ has been referred to in the preceding section. It lists each
                          activity required to complete a project giving each a reference and estimated
                          duration – usually in weeks. An assumption is made concerning the order in
   185   186   187   188   189   190   191   192   193   194   195