Page 195 - Civil Engineering Project Management, Fourth Edition
P. 195

success leads to another. By experience and force of his personality he may
                          pull the job ahead of schedule and complete before the promised time.
                          14.7 Completion                     Programme and progress charts   175
                          One of the duties of the engineer is to decide when the works can be considered
                          complete. Most contracts require that the works are substantially complete
                          before the engineer can issue his certificate of substantial completion. Unless
                          the contract has specific requirements to be met, substantial completion does
                          not require that every last item is finished, but it is generally taken to mean
                          that most of the works are done and the project can be put to safe and effective
                          use by the employer. There will no doubt be some items outstanding and
                          conditions, such as ICE (7th edition), allow for this while requiring that any out-
                          standing work is completed as soon as practicable during the defects period
                          or to an agreed timetable. Items left to be finished later would be those which
                          do not affect operation, such as painting; or may even include minor structures,
                          such as a gatehouse not essential to use of the works.
                            A shrewd contractor will be looking to get his certificate of completion as
                          early as possible and may apply to the engineer as soon as he thinks he has
                          any chance of it being allowed. Clause 48 of the ICE conditions (7th edition)
                          allows for such an application which must, however, be accompanied by an
                          undertaking to finish outstanding work. The engineer must then either issue
                          a certificate, or state what needs to be done to complete. The resident engineer
                          must advise the engineer of matters still to be completed and say if he consid-
                          ers the contractor’s application for completion is too early. Before the engineer
                          issues his certificate of completion he will need to check with the employer to
                          ensure that he has staff available to take over completed works.


                          14.8 Estimating extension of time


                          Failure to complete in time may make the contractor liable to pay liquidated
                          damages, as specified in the contract, to the employer. Hence at the time a
                          completion certificate is issued, the engineer must decide whether any exten-
                          sion of the time for completion is allowable. Extensions of time may have to
                          be allowed if the contractor is delayed by problems for which the employer is
                          liable under the contract. These should have been notified as they arose and
                          considered at the time (see Section 17.10). There may also be sections of the
                          work which the contract requires to be completed earlier than for the project
                          as a whole. It is important to note that not all delays will lead to an extension.
                          Some may not affect the path to completion and others may be matters for
                          which the contractor is responsible. It is necessary to check with the contract
                          conditions (such as ICE 7th edition Clause 44) to identify which delays are to
                          be taken into account, such as ‘exceptional adverse weather conditions’, etc.
   190   191   192   193   194   195   196   197   198   199   200