Page 197 - Civil Engineering Project Management, Fourth Edition
P. 197

177
                          Table 14.1
                                              Estimated Final Cost of Contract XYZ
                                                                      …etc.
                                                       Bill 1   Programme and progress charts  Total all
                                                              Bill 2
                                                                             General
                                                       (£)    (£)     (£)    contingency (£)  bills (£)
                          (a) Total of original bill items  ........  ........  ........  Excluded  ........
                          (b) Estimated change to      ........  ........  ........  ........  ........
                            bill items
                                                       ——     ——      ——     ——            ——
                          Revised bill items           ........  ........  ........  ........  ........
                          (c) Payable under VOs issued   ........  ........  ........  ........  ........
                             and pending
                          (d) Allow for further VOs    ........  ........  ........  ........  ........
                                                       ——     ——      ——     ——            ——
                          Total measured items         ........  ........  ........  ........  ........
                                                       ——     ——      ——     ——
                          (e) Dayworks:
                              Paid to date                                   ........
                              Allow for sheets in hand not yet paid          ........
                              Allow for further Dayworks to come             ........
                                                                             ——            ........
                          (f) Claims paid and claims agreed but not yet paid               ........
                          (g) Allow for
                              Claims pending not yet agreed                                ........
                              Possible other matters                                       ........
                                                                                           ——
                          Estimated total final cost                                     £ ........

                          Notes: (b) includes estimated extra costs due to increased quantities, less deductions for
                          items superseded by new items covered by VOs.
                          (c) is the total payable under VOs, divided over the bills as far as ascertainable, any
                          unallocated balance being put under general contingencies.