Page 187 - Civil Engineering Project Management, Fourth Edition
P. 187

Programme & Progress chart – Building



                                   3 Week  21  20  19  18  17  16  15  14  13  12  11  10  9  8  7  6  5  4  Position  Continued  to date  115  80  80  40  40  75  50  75  60  18  12  4  19  10  4  72  30  72  40  240  180  120  60  40  80  60  40  10  375  300  240  60  40  180  25  14  26  17  181  160  145  130  120  90  65  50  25  55  45  15  Actual time done and quantity Amount of work done

                                   2  110  115  115  60  30  10
                                   1

                                   Unit  m 2  m 2  m 2  m 2  m 2  m 2  m 2  m 3  m 3  m 3  m 3  m 3  m 3  Planned time and quantity
                                 Quantity                                                     Part of a bar chart for constructing a building

                                   No.  100  115  80  121  40  84  75  18½  72  240  375  25  181


                                      EXC. & filling soil stripping  Bulk excav.  Col. footings  Hardcore  Embanking  Seeding  Concrete Blinding  Wall found’s  R.C. Cols. to ground  R.C. Cols. to roof  Floors, Beams  Brickwork to ground  Above ground  Continued  Fig. 14.2.

                                  Description
   182   183   184   185   186   187   188   189   190   191   192