Page 185 - Civil Engineering Project Management, Fourth Edition
P. 185

167
                                                              Programme and progress charts
                          how any consequential delay to the contractor can be avoided. However he can
                          only make direct contact with nominated suppliers or sub-contractors before
                          the contractor places his order with them. After the contractor has placed his
                          order, any contact with a nominated sub-contractor or supplier must be via the
                          contractor, unless the contractor permits otherwise.
                            There may be other matters with respect to the programme the resident
                          engineer should look into. In some cases the employer may require access
                          through the project area for his other works. Or perhaps work by the con-
                          tractor must necessarily interrupt services which the employer relies upon,
                          such as electricity, drainage, water lines, etc. There may therefore be a strictly
                          limited time which the employer can tolerate such interruption; and he may
                          prefer the interruption to occur at some particular time of year rather than
                          another.
                            The influence of the weather may be an important factor to take into account
                          when examining a contractor’s programme, especially if the contract involves
                          substantial earthwork construction. The resident engineer may need to discuss
                          with the contractor where he thinks the programme should include optional
                          strategies according to weather. He should be able to advise what sort of meas-
                          ures could be taken to minimize the effect of weather.
                            The resident engineer has to appreciate that a contractor must ensure his
                          programme for construction fosters efficient, economic working. Once he has
                          brought men and machines onto the site he will want to use them continu-
                          ously until their tasks are completed. Also he will want their output to be as
                          near as possible to their maximum. Hence the resident engineer must appre-
                          ciate that, on occasion, a contractor has to ‘make do’ with what plant and men
                          he has on site, because the expense of bringing in more to do a ‘one off’ job
                          is too great to be economic. The resident engineer can only interfere when he
                          is certain that some method proposed by the contractor will result in unsatis-
                          factory work or some unacceptable risk to safety.



                          14.4 Watching and recording progress


                          From the agreed programme it is useful for the resident engineer to draw up
                          a list of dates by which different operations must be undertaken as shown in
                          Fig. 14.1. If there are several contracts let for the construction of a project, the
                          list will be essential for co-ordination of the work of different contractors. It is
                          useful as an overall guide for checking if the contractor is keeping to time and
                          as a reminder what future actions need to be taken.
                            Figure 14.2 shows a typical bar chart for a single structure. The length of the
                          broad bands show the time duration expected for each operation; these are
                          coloured or hatched in as work proceeds to show how much of an item of
                          work has been completed. The solid black lines indicate the actual time periods
                          taken to achieve the quantity entered in the broad band. Figures can be written
                          in to show the quantity of work done by the end of each week, as compared
   180   181   182   183   184   185   186   187   188   189   190