Page 254 - Civil Engineering Project Management, Fourth Edition
P. 254

Civil Engineering Project Management
                          234
                          natural ground has to be sufficient to mobilize adequate resistance from the soil
                          against pipe thrust. Where a bend points down, a weight block below the upper
                          joint is usually necessary, the joint being strapped down to it. Particular care
                          has to be taken when a bend down is required at the bank of a river or stream.
                          There may then be very little ground resistance to prevent the bend blowing
                          off if the joint is the usual push-in type, hence the upper joint of the bend may
                          require tying back to a suitable thrust block to resist the hydraulic force tending
                          to push the bend off.
                            The watertightness test for a pipeline should be prescribed in the specifica-
                          tion. Care must be taken to fill the pipeline slowly to ensure release of all air. The
                          usual practice is to fill from one end, having all washouts and hydrants open.
                          The latter are progressively closed along the line when they cease to emit air or
                          mixed air and water. This may take a considerable time, as air pockets may
                          get trapped and only slowly disperse. A satisfactory test cannot be achieved if
                          an air pocket is left in the pipeline. After filling, the pipe should stand under
                          pressure for 24h before testing. This permits pipe expansion and absorption
                          of water by asbestos cement or concrete pipes or by any mortar lining of steel or
                          iron pipes. Normally pipelines are tested between valves, but on a trunk main
                          these may be so far apart that temporary stop ends may be needed to test the
                          pipeline in reasonable lengths. Especial care is needed in testing partly com-
                          pleted pipelines to ensure they are properly restrained against the high test
                          pressures.
                            An experienced pipelaying contractor will know that care in making joints
                          on a pipeline is rewarded many times over when the pipeline test shows the
                          line is satisfactory. It is rarely possible to leave joints exposed before testing, so
                          if a test fails it may take much time and trouble to find the leak causing it. When
                          finally found it may be as simple as a twisted rubber ring in a push fit joint. It is
                          not easy to make clean perfect joints in a muddy trench. The contractor can
                          save himself money if he gives the jointer every facility to make a good joint –
                          easy access to see the underside of the pipe spigot, buckets of water and plen-
                          tiful clean rags to ensure that joint faces and joint ring are scrupulously clean
                          before the joint is assembled. No grease or jointing compounds should be
                          permitted other than that which the pipe manufacturer recommends. Welders
                          also need sufficient room and good lighting to make sure welds are adequate
                          and should not be expected to weld up badly aligned pipes.



                          18.9 Handling and jointing large pipes and fittings


                          All ductile iron or steel pipes and fittings must be handled with proper wide lift-
                          ing slings to prevent damage to their sheathing or coating. The use of chains
                          or wire ropes ‘blocked off’ pipes with pieces of wood should not be permitted
                          by the resident engineer. Apart from possible damage to the coating, the packing
                          pieces may slip out when the chain or wire rope slackens and the pipe may
                          fall. Handling of heavy pipes and fittings must be done with every precaution.
   249   250   251   252   253   254   255   256   257   258   259