Page 253 - Civil Engineering Project Management, Fourth Edition
P. 253

Earthworks and pipelines
                                                                                              233
                          minimum rise or fall. The preferred minimum gradients are 1:500 on a rising
                          grade in the direction of flow; and 1:300 on a falling grade. The former would
                          be to an air release valve, the latter from the air valve to a washout or hydrant.
                          Thus the levels of ground ahead of the pipelaying must be prospected to locate
                          suitable high and low points, and intermediate points where an increase or
                          decrease of grade is necessary. The pipeline between such pre-determined points
                          should follow an even grade. In flat ground it may not be possible to comply
                          with the foregoing grades, but it is still advisable to give uniform rises to air
                          valves and falls to washout positions. In built-up areas pipelines can generally
                          follow the requisite cover below ground surface because branches and connec-
                          tions will release air, and hydrants will be used as washouts.
                            Backfill to pipes should always be of selected soft or fine granular material
                          to 150mm above the crown of the pipe. Few contractors in UK would fail to
                          do this, but on some contracts overseas the resident engineer may need to stop
                          the contractor from dozing the excavated hard material straight back into the
                          trench irrespective of the rocks it contains which would at the least damage the
                          sheathing to pipes.



                          18.8 Thrust blocks and testing pipelines


                          The resident engineer may have to ensure that thrust blocks to pipes are
                          adequate. A block acts primarily to transfer pipe thrust to the natural ground
                          against which the block abuts. Hence, the nature of the ground is important.
                          The force to be resisted on a bend with push in joints is shown in Fig. 18.1. The
                          internal water pressure taken should be the maximum static pressure occur-
                          ring, plus an allowance for surge pressure. The block bearing area against the
























                          Fig. 18.1. Thrust on a pipe bend. The maximum pressure taken should be maximum
                          static plus an allowance for surge
   248   249   250   251   252   253   254   255   256   257   258