Page 248 - Civil Engineering Project Management, Fourth Edition
P. 248

Civil Engineering Project Management
                          228
                          the last 150–225mm of excavation, any loose material being either removed by
                          hand labour or rolled back with a light roller before placing of the base course for
                          a road or blinding concrete.
                            The presence of springs in a soft formation material exacerbates formation
                          finishing problems. Usually the specification will require spring water to be
                          led away by grips or drains to a pump sump which is continuously dewatered
                          to prevent softening of the formation. If springs are encountered and have not
                          been anticipated, or the method of dealing with them is not specified or shown
                          on the drawings, the resident engineer should report the situation to the engin-
                          eer. Special measures are often required to deal with springs to ensure safety
                          of the structure to be built on a formation containing them.
                          18.3 Haulage of excavated material


                          For large open excavations, such as when road cuttings have to be made and the
                          material tipped to form embankments, or for building an earth dam from open
                          borrow pit areas, the motorscraper is the most economical machine for excav-
                          ating, transporting and placing clays and clay-sand mixes. But the gradients
                          traversed need to be gentle and the motorscraper cannot pick up hard bands
                          of material or rock, unless ripping beforehand can break up the material suffi-
                          ciently. If hard or rocky material has to be excavated, the face shovel loading to
                          dump trucks has to be used, the trucks commonly having a capacity of 50–60t,
                          sometimes larger. However, neither scrapers nor dump trucks can traverse
                          public roads.
                            If the excavated material has to be routed off site via public roads to some
                          dumping area, the excavated material has to be carted away by tipping lorries
                          licensed for use on the public highway. Tipping lorries have a lesser capacity
                          than dump trucks, usually in the range 10–30t. A factor often having consider-
                          able influence when needing to transport material along public roads, is the
                          reaction of the local road and public authorities who may object to the extra con-
                          struction traffic and mud on the roads. If the local authority has also to give
                          planning permission for dumping spoil on some given land, such permission
                          may only be granted subject to restriction on the size of lorries used and their
                          frequency of passage. This situation cannot be left for tenderers to find out; the
                          employer has to obtain the necessary permissions and the contract must repro-
                          duce exactly the conditions laid down by the planning or other authority con-
                          cerned and require the contractor to conform to them. If the restrictions limit the
                          size and frequency of tipping lorries, the contractor may be forced to temporar-
                          ily stockpile excavated material on site and double handle it in order to conform
                          to his intended programme for construction and the haulage conditions laid
                          down. This will raise his costs for excavation.
                            Assuming there are no planning restrictions, the contractor needs to choose
                          that combination of excavating plant and haulage vehicles which achieves the
                          required excavation rate at lowest cost. The face shovel or backhoe output must
   243   244   245   246   247   248   249   250   251   252   253