Page 243 - Civil Engineering Project Management, Fourth Edition
P. 243

223
                                                                       Variations and claims
                          17.16 Arbitration
                          Under the ICE conditions, Clause 66, either the employer or contractor can
                          serve a Notice of Dissatisfaction on the engineer stating the nature of the matter
                          objected to. The engineer has to give his decision on this matter within one
                          month and, if either party is dissatisfied with it, they can issue a Notice of
                          Dispute. The purpose of this procedure is to eliminate matters which can be
                          resolved early by the engineer and to define any remaining dispute. A dispute
                          thus established can be resolved by ADR, adjudication, or arbitration.
                            Although arbitration may seem a reasonable way of finally settling a dispute,
                          it has disadvantages. It may take months to find an arbitrator both parties can
                          agree to and who is willing and able to act. Both parties may decide to employ
                          a lawyer to present their case because the dispute involves interpretation of the
                          terms of the contract. Also one party may need to employ the engineer to act as
                          witness, because the dispute also relates to the facts of the case, which lie in
                          records kept by the engineer. If the employer is disputing the engineer’s deci-
                          sion, this puts him and the engineer in a difficult position because the con-
                          tractor may wish to employ the engineer as his witness, but the engineer may
                          still be acting as engineer under the contract for ongoing work, and he can
                          sometimes be an employee of the employer.
                            The lawyers who present the case for each disputant, although chosen for
                          their experience of building contract disputes, may still fail to understand or
                          make use of significant technical data having a bearing on the dispute. They
                          may raise issues not previously in dispute, and use legal arguments concerning
                          the contract, which the disputants feel are not relevant to the real matters of con-
                          cern. Hence the outcome of an arbitration is uncertain and can be different from
                          what either of the parties expected.




                          17.17 Minimizing claims and disputes


                          The key precautions which can be taken to minimize claims and disputes are:

                          (a) adequate site investigations;
                          (b) checking that the works designed satisfy the employer’s needs and make
                             reasonable provision for his possible future requirements;
                          (c) completing all design drawings, specifications, and arrangements for incor-
                             poration of equipment purchased separately, before tenders for construction
                             are sought.

                          Under (b) the aim is to minimize changes during construction. Some may be
                          unavoidable if the employer needs alterations due to some new regulation
                          applying, or if his needs change due to something outside his control. But
                          often his possible (but uncertain) changes of need can be catered for cheaply by
   238   239   240   241   242   243   244   245   246   247   248