Page 250 - Civil Engineering Project Management, Fourth Edition
P. 250

Civil Engineering Project Management
                          230
                          Standards will be set in the specification for the permitted moisture content of
                          the fill before it is compacted, and its density after compaction. For example, the
                          specification may stipulate that fill type A must be compacted at a moisture
                          content between ‘optimum  1 per cent’ and ‘optimum  2 per cent’; while fill
                          type B must be compacted at a moisture content between ‘optimum  1 per cent’
                          and ‘optimum  3 per cent’. The optimum value is that determined by the stand-
                          ard compaction test, whether it is the 2.5kg hammer method (the original
                          ‘Proctor’ test) for embankments, or the 4.5kg hammer method as used for
                          roads. The density to be achieved will be specified as some percentage (e.g. 90
                          or 95 per cent) of the optimum under standard testing. Samples will have to be
                          taken from the fill to find the optimum moisture content and density under the
                          standard compaction test specified, and in situ density tests (see Section 12.11)
                          must then be undertaken by the resident engineer to ensure the right density
                          is achieved. Normally tests on fill materials will have taken place prior to the
                          design of the earthwork and the results of these tests and the method of testing,
                          etc. must form part of the data accompanying the specification. Care has to be
                          taken to ensure that the method of specifying the required end result covers
                          the range of materials likely to be encountered. It is then up to the contractor,
                          from his experience, to know what type of plant he must use to compact the
                          fill to the required standard.
                            Achieving the required moisture content may present difficulty. In wet
                          weather the borrowpit material may be too wet to use and the formation may
                          be too wet to work on. The resident engineer may have to instruct the con-
                          tractor to cease working when such conditions occur. There is little that can be
                          done to protect borrowpit material against excess rainfall. The formation can
                          be partly protected against rainfall by rolling it to a fall with a smooth wheeled
                          roller at the end of each day’s placing. Sometimes an attempt to protect the for-
                          mation by laying sheeting over it is adopted, but this is seldom practicable if the
                          site is windy. If the material is too dry for placing it must be watered. Although
                          watering at the borrowpit can be helpful it is usual to water-spray the spread
                          material from water bowsers. Some mixing of the material by dozer may be
                          necessary after watering to avoid only the surface material being wetted. In hot
                          dry climates more than the theoretical amount of water may need to be added
                          because of the high evaporation rate applying. A considerable amount of water
                          may be needed, involving the use of more than one water bowser.



                          18.5 Watching fill quality


                          When fill from a borrowpit is of variable quality the resident engineer needs
                          an inspector to watch the fill quality as placed, with power to reject unsuitable
                          material or call in the resident engineer in cases of doubt. Although the borrow-
                          pit must be examined to point out to the contractor where suitable and unsuit-
                          able materials appear to exist, the actual watch on material quality must take
                          place as it is dumped, spread and compacted. The characteristics of a material
   245   246   247   248   249   250   251   252   253   254   255