Page 73 - Civil Engineering Project Management, Fourth Edition
P. 73

58
                                                      Year 2
                                  Year 1
                                                         Manufacture
                                                                            Erect
                                       Design and drawings
                                T
                           1.   Civil Engineering Project Management       Year 3     Comm Test
                                                                                 Wiring
                           2.   T
                                                    Manufacture
                           3.               T                  Supply
                                                      Manufacture
                           4.                   T            Supply
                                                       2 months safety margin  on time
                                       Manufacture                  – do. –  First buildings ready  All buildings ready
                           5.    T              Erect      Start delivery  – do. –  Complete  delivery  Substantial  completion
                                            Civil wks
                           6.           T     Civil wk
                           7.                     T        Civil construction  Works
                                                                                        Finishing
                                                                                         sub – c
                                                        Manufacture
                           8.                   T                       Test Del  Install  Comm Test
                           9.                                                       Install  Test
                                       T   Tendering period
                                       Contract No.
                                       1. Process plant  4. Pipe supply  6. Site preparation
                                           Electrical subc.  5. Swing bridge  7. Main civil works
                                       2. Site investigations      Plant  8. Pumping plant
                                       3. Valve supply       Civil subc.  9. Instrumentation
                          Fig. 5.1.  Planning the co-ordination of contracts for a water supply project


                          the cost of getting the construction contractor to temporarily store some plant
                          on site – will be less than the cost of delaying construction.
                            An alternative is for the employer to pass to the construction contractor the
                          responsibility for arranging delivery of plant as he needs it. This was done on
                          the Mangla dam project in Pakistan where eight major suppliers for hydro-
                          electric plant, gates, valves and other large equipment were involved. The civil
                          contractor was required to take over the plant supply contracts and arrange
                          delivery to suit his construction programme, after such plant had been tested
                          to the satisfaction of the employer. This kind of approach, however, is only
                          practicable where the project is so large, as at Mangla, that construction takes
                          several years to complete.


                          Site preparation contracts


                          An employer may also let a separate civil engineering contract for site-
                          preparation, which covers building of access roads, bulk excavation, and pro-
                          viding electrical, water, and sewerage services to the site. Housing for site
   68   69   70   71   72   73   74   75   76   77   78