Page 74 - Civil Engineering Project Management, Fourth Edition
P. 74

Preparing contract documents
                                                                                               59
                          personnel may also be included. This contract can be let while detailed design
                          of the project is still ongoing, and can therefore contribute to early project com-
                          pletion. Other advantages are that some excavation can be left open for the
                          civil works tenderers to view, so minimizing the risk of claims for unforeseen
                          ground conditions, and arrangements can be made for temporary storage of
                          pipes and valves, etc. the employer orders which the main contractor has to
                          incorporate in the works. However a site contract must be completed before
                          the main civil engineering contract is let.
                          Co-ordination requirements

                          When separate plant supply contracts are let, the main civil contract must
                          include all details of what the civil contractor must do in connection with such
                          plant. Among the matters to be specified and allowed for in the bill of quan-
                          tities are the following:
                          • Items requiring the civil contractor to take delivery of plant, offload, store,
                             protect, and insure it.
                          • Items requiring the contractor to check deliveries of plant as invoiced by
                             the supplier, inspecting items for any damage, and drawing the attention
                             of the employer’s engineer to any such, and to missing items.
                          • Where the plant supplier is to erect his plant, the main civil contract must
                             state what services the civil contractor is to provide the supplier with, such
                             as – access, scaffolding, lifting gear, power and lighting, water, use of the
                             contractor’s canteen and toilets, etc.
                          • Where pipes or other plant items have to be built in the civil works, the
                             contract must make clear whether such items have to be built in ‘as the
                             work proceeds’ or whether a hole can be left for a pipe to be ‘built in after’.
                             The contract drawings should show how the latter has to be done, and
                             who is to be responsible for positioning any such item correctly.
                            The ‘interface’ between all separate contracts has to be carefully checked to
                          ensure that all matters to be done by the plant supplier or civil contractor are
                          properly covered and none missed out. The principal responsibility for this will
                          lie upon the employer’s engineer in charge of design and the drawing up of
                          contracts. On a large scheme where several teams of engineers work on differ-
                          ent parts of the design, checking that the interface between their separate parts
                          match, is equally important.



                          5.7 The specification of general requirements


                          In Section 5.5 some problems of writing specifications have been mentioned.
                          A specification usually comprises two distinct parts – Part 1: all the general
   69   70   71   72   73   74   75   76   77   78   79