Page 77 - Civil Engineering Project Management, Fourth Edition
P. 77

Civil Engineering Project Management
                          62
                            In drawing up the specification it is advisable to plan out beforehand subjects
                          to be dealt with. An order such as the following might be adopted.
                           1. demolition, site clearance;
                           2. excavation;
                           3. piling;
                           4. concrete;
                             (a) in situ;
                             (b) reinforcement;
                             (c) formwork;
                             (d) pre-cast;
                             (e) pre-stressed;
                           5. pipe-laying (might be put later);
                           6. steelwork (structural);
                           7. brickwork/blockwork/masonry;
                           8. roofing;
                           9. cladding (if special);
                          10. carpentry;
                          11. finishing trades (as necessary);
                          12. roads, site restoration, fencing.
                          It is not advisable to use three or more levels of decimal numbering of sections,
                          such as ‘2.1.1’, ‘2.1.2’, etc. Only the section headings under each class of work
                          need be numbered; sub-sections can be un-numbered and identified by a left
                          hand heading, and paragraphs are not numbered. This permits insertion of late
                          additions without disturbing any numbering.
                            When drafting the specification, care should be taken to ensure coverage of
                          all types of work that appear on the drawings. In civil engineering contracts
                          the specification sets out all quality requirements so these must be complete.
                          The items in the bill of quantities only need sufficient description for the item
                          to be identified for the purposes of payment. If an item in a bill of quantities
                          appears with extra description which is not in the specification, a contractor
                          might argue that the item with the added description requires additional pay-
                          ment. (See Section 4.4 where it is noted that under JCT conditions for building
                          work the contrary practice applies.)
                            There have been differences of opinion among engineers as to the merits of
                          ‘method’ as against ‘performance’ types of specification. A method specification
                          for concrete quotes not only the materials and quantities of them to be used to
                          make various grades of concrete but also the strengths and other physical char-
                          acteristics to be achieved together with requirements for handling and placing.
                          A ‘performance’ specification would stipulate only the strength and other phys-
                          ical characteristics to be achieved. This, it is said, leaves the contractor greater free-
                          dom to decide how he will achieve the performance criteria. However, opponents
                          of performance specification point out that control by testing is only possible
                          (in the case of concrete) 28 days after placing, and such tests may not provide
                          sufficient proof that the structure will perform satisfactorily in the long term.
                          If defects appear later, how is the contractor to be held responsible? Traditional
   72   73   74   75   76   77   78   79   80   81   82