Page 77 - Puret Sound Energy Hand Book 1218
P. 77

Chapter 8


              Table 8              Example of overhead and underground modified service

                                           Customer request             PSE and Customer responsibilities
                                    Overhead Modified Service          •  Notify your CCS Representative if you
                                    Your electric meter base is being    are changing panel amperage rating or
                                     replaced with a new meter base,     increasing the connected load within
                                     and will be located a few feet away   your building.
                                     from where old meter base was.    •  You or your electrician must arrange for
                                    You will also replace the existing   PSE to remove the wire from the point
                                     mast and weatherhead.               of attachment and make permanent
                                                                         connection to the new weatherhead.
                                                                        You must give PSE adequate notice of
                                                                         your intentions, typically 5 to 10 working
                                                                         days prior to needing your service
                                                                         energized.
                                                                       •  An electrical permit must be present
                                                                         and visible prior to PSE energizing your
                                                                         service.

                                    Underground Modified Service       •  Notify your CCS Representative if you
                                                                         are increasing the load or capacity of
                                    Your mobile home is being relocated   your meter panel.
                                     and you need to move your meter
                                     pedestal closer to the new location.   •  You are responsible for digging to the
                                    Or, you are remodeling and have to   new pedestal location.
                                     change the electrical panel and/or   •  You must expose PSE’s wire or conduit
                                     meter location.                     at the old pedestal location. This is
                                                                         where your new trench will start.
                                                                       •  A new pedestal installation permit must
                                                                         be present and visible on-site prior to
                                                                         calling PSE to perform the work. You
                                                                         must give PSE 5 to 10 working days'
                                                                         notice prior to calling PSE to perform
                                                                         the work.































               Electric Service Handbook 2017 — Single-Family Residential Projects                          68