Chapter 7
Figure 37 Temporary overhead service installation
8
6
TOP VIEW OF STUD AND BRACES
ALIGN SERVICE LINE BETWEEN BRACES.
MAX 70' IN LENGTH WITHOUT PSE APPROVAL.
7
1 45˚
2
10' MIN 9
TO DRIP
LOOP
12' 3
MIN NOTE THAT THE SERVICE LINES
EXTEND AT A 45˚ ANGLE FROM
WITHIN THE BRACES.
6' MAX
5' PREFERRED
4' MIN
4
5
GROUND LINE 24" MIN
8' MIN
Items owned and installed by customer Items owned and installed by PSE
4" x 4" x 16' or 2" x 10" x 16' minimum, 8 Service line
1
continuous single structure 9 Meter
Meter socket and distribution panel (up to
2
200 A, 120/240 V)
3 Ground wire, in accordance with NEC/WAC
4 Ground rod(s), in accordance with NEC/WAC
5 2" x 4" brace (two required)
Service entrance conductors - 18" out of
6
weatherhead minimum
7 Insulated clevis (point of attachment)
Electric Service Handbook 2017 — Single-Family Residential Projects 66