Page 100 - B8773-AEW-XX-XX-PP-A-0001_[P1]_Contractors Manual
P. 100

5.1.3 The Contractor                                It is one of the standard DP UK&I Ltd conditions
                                                    that the shopfitting company acts as “Principal
will be responsible for and will be deemed to       (Main) contractor”. As such it is the shopfitter’s
have included in his price for:                     responsibility to contact ALL other suppliers
•	 undertaking role of Principal Contractor in      and contractors and ensure that their delivery
                                                    and/or installation dates are arranged and
    accordance with the CDM Regulations 2015        confirmed to suit the shopfitter’s programme.
•	 undertaking construction phase under CDM
                                                    However, it is the main contractor’s responsibility
    Regulations                                     to ensure all facilities are in place to enable
•	 preparing construction phase Health and          others to complete their works on the appointed
                                                    days i.e. electrical works advanced enough to
    Safety plan prior to commencement of the        allow phone installation, etc.
    works
•	 liaising with Building Control/Approved          Where appropriate, the Principal Contractor
    Inspector, ensuring all works comply with       is issued with a copy of the Domino’s
    building control and fire officer               purchase order schedule with contact details.
•	 coordinating with the statutory services         Other suppliers are normally given a “week
    provider and integrating service providers’     commencing” delivery date. The Principal
    work into the construction programme,           Contractor must therefore plan the works
    providing attendance where necessary            and make arrangements for specific dates
•	 undertaking detailed setting-out survey          as required. Be aware that some suppliers
    prior to commencing manufacture or fit-out      have significant lead times. DO NOT expect
    and advising the PM/Design Team of any          immediate delivery. If there are problems with
    significant variances                           cooperation and availability from suppliers, the
•	 coordinating with and integrating into the       Employer should be advised as soon as possible.
    construction programme, delivery and
    setting out of items supplied by others         If site events require a change to a previously
•	 providing comprehensive Health and Safety        booked date, the Principal contractor MUST
    file on completion of the works incorporating   rearrange, providing as much notice as possible.
    the Operation and Maintenance manual            Charges for abortive visits due site conditions, will
•	 responsibility for the security of the site and  be charged back to the Principal Contractor.
    insurance of works during the contract
•	 delivering the finished project within           The Principal Contractor must prepare and
    the programme agreed at the time of             issue a detailed construction programme
    accepting instruction from the employer to      highlighting tasks, deliveries and critical dates to
    proceed with the works, including the price     the Employer/Project Manager before starting
    for necessary out of hours, or weekend work     on site. Deviations from the programme must be
•	 acting as keyholder for the duration of the      reported immediately.
    works and to make suitable arrangements
    so access to the premises is available at all
    times in the event of emergencies