Page 104 - B8773-AEW-XX-XX-PP-A-0001_[P1]_Contractors Manual
P. 104

5.2.2 General Accuracy/Setting Out                      5.2.3 General Services

Appearance and Fit:                                     Service Regulations:
•	 Arrangethesettingout,erection,juxtaposition          •	 Any work carried out to or which affects new

    of components and application of finishes               or existing services must be in accordance
    (working within the practical limits of the             with the Bye Laws or Regulations of the
    design and the specification) to ensure that            relevant Statutory Authority.
    there is satisfactory fit at junctions, that there
    are no practically or visually unacceptable         Service Runs:
    changes in plane, line or level and that            •	 Make adequate provision for services,
    the finished work has a true and regular
    appearance.                                             including unobstructed routes and fixings.
•	 Wherever satisfactory accuracy, fit and/                 Wherever possible ducts, chases and holes
    or appearance of the work are likely to                 are to be formed during construction rather
    be critical or difficult to achieve, obtain             than cut.
    approval of proposals or of the appearance
    of the relevant aspects of the partially            Mechanical and Electrical Services:
    finished work as early as possible.                 •	 final tests and commissioning must be
•	 Without prejudice to the above and unless
    specified otherwise, tolerances will (where             undertaken out so that they are in full
    applicable) be not greater than those given             working order at Practical Completion.
    in BS 5606, Tables 1 and 2.
                                                        5.2.4 Supervision/Inspection/ Defective Work

                                                        Supervision:
                                                        •	 In addition to the constant management

                                                            and supervision of the works provided by the
                                                            Contractor’s person in charge, all significant
                                                            types of work must be under the close
                                                            control of competent trade supervisors to
                                                            ensure maintenance of satisfactory quality
                                                            and progress.

5.2.2  General Accuracy/Setting Out                     3 February 2016