Page 104 - B8773-AEW-XX-XX-PP-A-0001_[P1]_Contractors Manual
P. 104
5.2.2 General Accuracy/Setting Out 5.2.3 General Services
Appearance and Fit: Service Regulations:
• Arrangethesettingout,erection,juxtaposition • Any work carried out to or which affects new
of components and application of finishes or existing services must be in accordance
(working within the practical limits of the with the Bye Laws or Regulations of the
design and the specification) to ensure that relevant Statutory Authority.
there is satisfactory fit at junctions, that there
are no practically or visually unacceptable Service Runs:
changes in plane, line or level and that • Make adequate provision for services,
the finished work has a true and regular
appearance. including unobstructed routes and fixings.
• Wherever satisfactory accuracy, fit and/ Wherever possible ducts, chases and holes
or appearance of the work are likely to are to be formed during construction rather
be critical or difficult to achieve, obtain than cut.
approval of proposals or of the appearance
of the relevant aspects of the partially Mechanical and Electrical Services:
finished work as early as possible. • final tests and commissioning must be
• Without prejudice to the above and unless
specified otherwise, tolerances will (where undertaken out so that they are in full
applicable) be not greater than those given working order at Practical Completion.
in BS 5606, Tables 1 and 2.
5.2.4 Supervision/Inspection/ Defective Work
Supervision:
• In addition to the constant management
and supervision of the works provided by the
Contractor’s person in charge, all significant
types of work must be under the close
control of competent trade supervisors to
ensure maintenance of satisfactory quality
and progress.
5.2.2 General Accuracy/Setting Out 3 February 2016