Page 4 - B8773-AEW-XX-XX-PP-A-0001_[P8]_Contractors Manual
P. 4

The Contractor











       Will be responsible for and will be deemed to         It is one of the standard DP UK&I Ltd conditions
       have included in their price for:                     that the shopfitting company acts as “Principal
       •  undertaking  role  of  Principal  Contractor  in   (Main) contractor”. As such it is the shopfitter’s
          accordance with the CDM Regulations 2015           responsibility to  contact  ALL  other  suppliers
       •  undertaking construction phase under CDM           and contractors and ensure that their delivery
          Regulations                                        and/or  installation  dates  are  arranged  and
       •  preparing  construction  phase  Health  and        confirmed to suit the shopfitter’s programme.
          Safety plan prior to commencement of the
          works                                              However, it is the main contractor’s responsibility
       •  liaising  with  Building  Control/  Approved       to  ensure  all facilities  are  in place to  enable
          Inspector,  ensuring  all  works  comply  with     others to complete their works on the appointed
          building control and fire officer observations     days i.e. electrical works advanced enough to
       •  coordinating  with  the  statutory  services       allow phone installation, etc.
          provider  and  integrating  service  providers’
          work  into  the  construction  programme,          Other  suppliers  are  normally  given  a  “week
          providing attendance where necessary               commencing”  delivery  date.  The  Principal
       •  undertaking  detailed  setting-out  survey         Contractor  must  therefore  plan  the  works
          prior to commencing manufacture or fit-out         and  make  arrangements  for  specific  dates
          and  advising  the  PM/  Design  Team  of  any     as required.  Be aware  that  some  suppliers
          significant variances                              have  significant  lead  times.  DO  NOT  expect
       •  coordinating  with  and  integrating  into  the    immediate delivery. If there are any problems
          construction  programme,  delivery  and            with cooperation and availability from suppliers,
          setting out of items supplied by others            the  Employer  should be  advised as soon  as
       •  coordinating with the client on direct trades      possible.
          and orders
       •  providing comprehensive Health and Safety          If site events require a change to a previously
          file on completion of the works incorporating      booked  date,  the  Principal  Contractor  MUST
          the Operation and Maintenance manual               rearrange, providing as much notice as possible.
       •  responsibility for the security of the site and    Charges for abortive visits due site conditions, will
          insurance of works during the contract             be charged back to the Principal Contractor.
       •  delivering  the  finished  project  within  the
          programme  instruction  from  the  employer        The  Principal  Contractor  must  prepare  and
          to  proceed  with  the  works,  including  price   issue  a  detailed  construction  programme
          for necessary out of hours, or weekend work        highlighting tasks, deliveries and critical dates to
       •  acting as the keyholder for the duration of the    the Employer/ Project Manager before starting
          works  and  to  make  suitable  arrangements       on  site.  Deviations  from  the  programme  must
          so access to the premises is available at all      be reported immediately to the client and
          times in the event of emergencies                  Domino’s Project Manager.
   1   2   3   4   5   6   7   8   9