Page 25 - Internal Auditor M.E. - June 2019
P. 25

construction audit



          contractually, however, variations can take many forms, in the   Log also provides the status of variation order i.e. approved,
          manner they arise, which are defined by FIDIC (Red Book) as   rejected, disputed, in process etc. Comprehensive logs may also
          below:                                            carry percentage of completion for each variation, showing the
                                                            status of works.
           1)   Variation initiated by Engineer or Employer
                                                            While selecting a sample, auditor should consider the quantum of
           Variation clause(s) in the contract permits the employer to   engineering instructions received, variations submitted, general
           make amendments in the contract’s elements and this ensures   status of approvals, values, certifications and work performed. A
           responding to practical needs of the project. These changes can   sample may be selected considering the impact on cost or activity
           be additional works, modifications or omissions (full or partial   e.g. works on a variation for an activity affects project’s critical
           descoping or deletion of an activity or element).   path, which results in extension of time.
           Changes can also include ‘Acceleration order or Sequence
           changes’ which is generally required to complete the works
           prior to agreed completion of the project. The works included   Audit Objectives
           as provisional sums in the BOQ can be executed using variation   The key audit objectives for variation reviews are:
           order. Any other minor or incidental nature of works are
           required to be carried out in a day work basis (FIDIC, Red   •  To provide assurance on the design and effectiveness of the
           book).                                              internal controls for variation management;
                                                              •  To ensure compliance with policies & procedures and with
           2)  Variations initiated by Contractor              applicable rules & regulations;
           For reasons attributable to the contractor or when value   •  To ensure ‘variation workflow procedures’ make the most
           engineering is part of the scope, the contractor may work on   efficient use of the available resources.
           an acceleration plan and intends to complete the project earlier
           than planned. In certain circumstances, contractor may identify   •  To ascertain that the required knowledge, skill and
           certain additional works to be carried out, eventhough not   competency is resourced.
           specifically part of scope. In this scenario, contractor identify
           these works for approval of Engineer and Employer. In a dispute   Review Scope Outline
           situation, the same can be part of contractor’s claim.
                                                            Following are the recommended scope review areas which should
           3)  Other categories of Variations               be considered for testing analysis on variations to the contract.
           The other categories may include re-measured contracts,
           whereby any change in quantities may be claimed via a variation   Timely communication   Variation orders are approved
           order. There may be other situations like technical errors in   Cost and Cause Assessment  Conditions agreed
           contractual terms or design and force majeure which may give   Methodology and procedure to   Compliance with policy &
           rise to variation orders.                             establish a variation  procedure and contractual
          A variation for addition in the scope or an omission for descoping                requirement
          can arise from any of the categories.              Follow-up and dispute resolution   Variation - Claimed in payment
          During Audit Planning Phase (ref: Audit Process) auditor should   procedure       applications
          obtain the basic understanding of the type and complexity of   Documentation and audit trail  Back to back contracts
          the project, contractual requirements for variations vis-à-vis
          nature and type of variations. Auditor should update the audit   Staff competence and efficiency  Management Reporting
          programme considering the special conditions, timelines, agreed
          methodology, key risk areas and materiality.
                                                            The auditor should always consider circumstances having a
                                                            material impact on variation management. One of those situations
                                                            can be absence of robust procedure to capture variations and out
          Variation Log                                     of scope works which can directly affect the project’s profitability
          The first basic document, which provides an overview of the   and can cause cost overruns. With review of correspondence and
          variations’ status is “Variation Log”. Log provides information   minutes, an auditor should always be vigilant about situations
                                                            giving rise to variations.
          about type of variations (generally separate logs are maintained for
          each category), status of submission, description of variation to the   Another situation can be delayed or missed notifications and
          contract, reference to the engineering instruction and reference   submissions, which may not only be classified as noncompliance
          to the letters and notifications, submission/claim value, internal   of the contractual terms but can cause rejections or delay in cash
          value and value attributable to the subcontractor. Log may also   flows.
          have certification and/or back to back status of certifications with   The following process flow provides the basic understanding of a
          subcontractors.                                   generic audit process flow, embedded with variations review: