Page 27 - Internal Auditor M.E. - June 2019
P. 27

TO cOMMenT on the article,
              eMail the author at Tauseefahmed.aca@gmail.com                              construction audit



          Variation / Omissions Cost Assessment             main contractor should incorporate these claims while claiming
                                                            for a relevant activity. In case of approving or certifying any
          Under clause 13.3 of FIDIC Red Book, each variation shall be   variations, the approval and certification should not be more than
          evaluated in accordance with Clause 12 (Measurement and   the approval / certification received. The same should be applicable
          Evaluation).                                      in cases of advance payments, advance payment guarantees,
          An auditor should enhance his knowledge over the contractual   performance guarantees or retention against variations, however
          requirements and special conditions appended to the contract,   some exceptions always remains as the conditions of the specific
          prior to reviewing variations. A contract would invariably provide   project desires. The auditor needs to understand those conditions
          a mechanism for variations and method of payment thereof.   and fairly document the same.
          Any works done via engineering instructions (EIs) or approved
          variation orders are included in payment application.
                                                            Key Risk Areas
          By review of EI log or correspondences and minutes of meetings,   1)   Unidentified or late identification of Variations:
          the auditor should review situations where, works are done
          without approval. In this scenario contractor has executed works   Absence of procedure or skill to timely capture the variation
          on his own discretion and can be contractually rendered as having
          no right of payment.
                                                              2)   Unidentified impact over Extension of time:
          For verification of cost assessed by management, the auditor may
          select a representative sample of cases. Rates used in the variation   Absence of procedure or skill to assess impact of variation
          orders can be verified against bill of quantity (BOQ). There might   on critical path
          be cases where BOQ rates are not being used for e.g. similar
          items are not available in the BOQ, then, generally a new price is
          agreed. In case, works must be executed without delay while rate   3)  Late notifications:
          is not agreed, then a provisional rate or amount is approved or on   Lack of control over contractual requirement may have
          account payment is permitted. An auditor should also look for   impact over approval of variations as late notifications can
          situation of disagreements on prices and rates and review the same.   be considered as noncompliance, therefore can create a risk
                                                                 of rejection of valid claims.

          Extension of Time Impact
                                                              4)  Incorrect valuation:
          Clause 8.4 (Extension of Time for Completion) and Clause
          20.1 (Contractor’s Claims) of FIDIC Red Book are applicable in   Absence of a robust procedure over variation cost
          extension of time claims.                              assessment.
          Variations, usually increases the scope and may have an impact
          on completion time. Auditor needs to ensure that management
          has implemented a procedure to review impact of variation works   Conclusion
          on critical path. In such cases, timely notifications are served, and   Variations may be initiated at any time prior to issuing the Taking-
          extension of time approval is requested, which should be followed   Over Certificate for the Works, either by an instruction or by a
          by cost claims for extension of time.
                                                            request for the Contractor to submit a proposal. The Contractor
          Clause 20.1 of FIDIC Red Book stipulates a timeline of 28 days   shall execute and be bound by each Variation (Clause 13.1 FIDIC
          within which Contractor shall serve a notice to the Engineer,   Red Book).
          describing the event or circumstances given rise to the claim.
          The auditor should review EIs, correspondences and minutes of   An auditor must establish an understanding over contractual
          meetings for delayed and unserved notices, in order to ensure that   requirements for variation. The audit program should be
          timely action is taken to avoid risk of unserved or delay notices   prepared around this requirement, considering key risk areas. The
          and risk of liquidated damages. In similar perspective, a claim is   materiality should also be considered while allocating resources
          served by the Contractor within 42 days (Under Clause 20.1).   for the scope. During Planning phase, auditor should allocate
                                                            weightage to the variations’ review and scope to be covered.
          The parties have right to use different timelines with mutual   This is followed by review of policies and procedures and basic
          consent.
                                                            mechanism established to capture variations, valuation, work
                                                            execution and claim.
          Back to Back contract
                                                            Tauseef Ahmed, Fca, aca (icaeW),  cia,  cFe,  ciSa, audit Manager,
          The auditor needs to gain knowledge of subcontractors claims. The   arabtec Holding PJSc

          JUNE 2019                                                           INTERNAL AUDITOR - MIDDLE EAST     27
   22   23   24   25   26   27   28   29   30   31   32