Page 403 - Installation Training Binder FIT1-3
P. 403

B. Check Barrier Layout

                       1.  Layout Barrier per CAD Diagram
                       2.  Verify barrier wall fits around rack, stack or cabinet with 1” of clearance
                          (Figure 5)
                       3.  Check for Obstructions (Figure 6)


















                                   Figure 5                                   Figure 6
                   C. Liner Preparation

                       1.  Line up a T-square or other straight tool to one side of a rack stanchion
                          (Figure 7)
                       2.  Mark line from beginning of rack to end of the straight edge (Figure 8 and
                          Figure 9)










                                        Figure 7                                Figure 8
                       3.  Repeat process for each side of stanchion
                       4.  Ensure liner is firmly taped to ground before moving to next stanchion


















                                                             Figure 9
                   EnviroGuard  800-206-9884     Fax  909-624-1772                     www.egsintl.com

                   11/07 rev. A      Condor-Plus System Retrofit Installation Setup Instruction      - 4 -