I. Install Barriers

                          Always check for rebar or underground obstructions before drilling!

                       1.  Using the drill bit provided, drill holes to 1” depth at previously marked
                          locations. Clean drill holes as you go (Figure 22).
                       2.  Insert drop-in floor anchors and insure top of anchor is flush with floor.
                       3.  Place containment walls back over the perimeter to check alignment and
                          hole accuracy.
                       4.  Using the anchor punch tool set the drop-in floor anchors into the floor.










                                                       Drill to 1” depth

                                    Figure 22                                        Figure 23
                       5.  Make sure the floor is clear of any debris.
                       6.  Place the floor anchor bolts in the drop-in floor anchor assemblies and
                          hand tighten the floor anchor bolts (Figure 23).
                       7.  After all components have been situated, continue to secure the
                          containment wall to the floor by tightening the floor anchor assembly bolts
                          using a 7/16” socket.















                                                          Figure 24


                       8.  In the event that height of the liner exceeds the containment walls, trim the
                          liner as necessary after liner has been pushed fully into containment.
                       9.  Install the extrusion clips over containment walls and liner.










                   EnviroGuard  800-206-9884     Fax  909-624-1772                     www.egsintl.com

                   11/07 rev. A      Condor-Plus System Retrofit Installation Setup Instruction      - 9 -
   403   404   405   406   407   408   409   410   411   412   413