Figure 5-1: Projection option box in the Default Parameters and Options menu.

               5.1.2             Simulation Status

               After the PRJ system is selected, the Status Bar (see Section 2.2) will provide information on the current
               status of the model submitted for simulation (see Table 5-1 for examples).  Pay attention to the progress of
               the model.  If there is an issue with the simulation process, an error message will be shown (see the last row
               in Table 5-1).  Sometimes simply re-submitted the model for simulation will alleviate the issues (e.g., if
               there is an issue reaching the IGW server). In other cases, editing/refinement if input data/files may be
               necessary (e.g., if the format for user input file is not correct).

                        Table 5-1: Examples of Status Bar messages displayed while submitting a model for simulation
















               After  the  head/solute  distribution  is  solved  for  the  initial  time-step,  the  Status  Bar  will  read  “Done:
               Geo/comp …. In progress”. The resulting head (and solute distribution) will be shown within the model
               display in the MDWA (see  Figure 5-2 for an example).   A cross-section, shown as a yellow polyline
               spanning the entire model from west-east (W-E) along the central portion of the domain, is automatically
               generated for visualizing vertical characteristics of the aquifer system (see Section 5.4). Customizing the
               display of results is explored in the next section.