• Details of building storefront, to observe the progress of the work and to
entrances, and window details, and answer questions regarding the construction.
• Schedule for doors, frames, and The MPEFP engineer has included three (3)
hardware. site visits during construction including the
■ The structural engineer will prepare pre-final substantial completion observation.
drawings that will represent the design The structural engineer has not included site
of the footings and foundations, precast visits; however, they have included seven (7)
concrete wall panels, and details as online construction progress calls. Additional
required to communicate the primary site visits can be provided on an hourly basis
building framing system. including travel time and expenses.
■ Coordinate our services with those of the ■ We will provide shop drawing review and
Owner’s consultants. processing of architectural, structural, and
■ Attend coordination meetings to review the MPEFP components required by the contract
progress of the drawings. documents. One (1) review of each required
■ Provide construction documents of the submittal plus one (1) follow-up review is
MPEFP systems. included provided the submittal is made in
■ Provide signed and sealed drawings for use accordance with the contract documents. The
in the building permit application process. following shop drawings and submittals will be
■ Prepare COMcheck Compliance reviewed:
Certificates. • Concrete wall panels (architectural
features),
Bernardon will attend meetings with you in your • Miscellaneous metals (roof ladder, railings,
local office as required to finalize the scope of these steps),
design services. Bernardon has included three (3) • Aluminum and glass,
in-person meetings for this phase. Additional in- • Doors, frames, and hardware,
person meetings if requested will be provided on an • Dock equipment,
hourly basis. Online collaboration meetings will be • Roofing,
provided as needed. • Structural components, and
• Mechanical, plumbing, and electrical
Phase 3 – Construction Contract Administration components.
(Limited Scope) ■ Answer contractor Requests for Information
During the Construction Contract Administration (RFIs). We have included a budget of forty (40)
phase of the project, we will provide the following hours for this service.
services:
Please note that it is our goal to maintain flexibility
■ Respond to comments from the building plans in the performance of our services during this
examiner. phase and render the most appropriate level of
■ Bernardon will attend one (1) on-site pre- service. We can modify our scope of services upon
construction meeting and up to eighteen your request with an adjustment in compensation.
(18) on-site construction progress meetings
BERNARDON | Response to Request for Proposal for Design Services Page 32
101 Independence Lane Associates LLC | August 5, 2022