Page 156 - Bahrain Gov Annual Reports (II)_Neat
P. 156

8
                         Five hundred new rifles and half a million rounds of ammunition   were
                   bought and the State Police Force was increased by over fifty men.
                         5. Departmental Expenses.
                               Budget estimate      Rs. 10,720
                               Actual expenditure    „  23,800
                         Additional furniture, typewriters and oflice equipment were purchased
                   owing to the expansion of various departments. This heading includes postage,
                   printing and stationery.
                         6. Education.
                              Budget estimate      Rs. 1,06,500
                              Actual expenditure    „   1,03,079
                      Expenditure was Rs. 3,000 less than the allocated amount. It included cost of
                  additional machinery and equipment for the Technical School, allowances to
                  eighteen students in the Engineering and Carpentry classes and expenditure of the
                  Ruling Family in England, India and Syria.
                        7. Municipalities.
                                  Budget estimate    Rs. 50.400
                                  Actual expenditure  „ 50,400
                        This represents the regular allowances which are made to the two munici­
                  palities.
                        8. Public Works.
                                Budget estimate
                                  New buildings   Rs. 5,33,000
                                  General repairs   „   15,000
                                  Roads             „ 20,000
                                                  Rs. 5,68,000
                                  Actual expenditure „ 4,29,170
                        Estimates for buildings were made by the new Public Works Department at
                  the begining of the year when the department had little experience in calculating
                  costs of bailding,f Dr this reason the expenditure on many of the buildings has exceeded
                  the estimate.
                        Certain important works were not undertaken and other works, for which no
                  provision was made, were carried out.
                        New Works, Major.
                        a.  Palace* Not proceeded with
                        b.  Hospital. Budget estimate  Rs. 80,000
                                    Actual expenditure „   60,440
                        When the Budget was prepared it was proposed that the men’s and women’s
                  hospitals should be contained in one building. The plans were revised because more
                  land was obtained and the male and female blocks are now separate. The staff of the
                 # women’s hospital, doctor, matron, and nurses is to be accommodated in two wings of
                 * the hospital building The women’s hospital and quarters were partially constructed
                  during the year.
                        C. Dispenuury Sc Medical Officer** Quarters.
                              Budget estimate     Rs. 45,000
                              Actual expenditure   „   67,781
                        Provision for this building was inadequate, the cost of land reclamation and
                  sanitary fittings greatly exceeded the estimated sum. This building contains dispen-