9
        sary and waiting rooms, consulting rooms, eye treatment rooms, washing rooms
        etc. etc. for men and women.
              On the first floor there is a flat for the Medical Officer.
              d. Extension of Customs Pier.
                    Budget estimate     Its. 50,000
                    Actual expenditure   „   19,264
              The work was begun towards the end of the year, two sections, each 200 x 50
        feet, were completed.
              6. Passport Office.  Not Proceeded with.
             /. Residential Quarters. Not proceeded with.

             g.  A house was built at Kozabia on land previously acquired by the Govern­
        ment. The cost of this building, including fittings etc , was Rs. 43,460. The house is
        leased by H. B. M’s Political Agent as a residence for the Assistant Political Agent.
              h.   Manama-Muharraq Causeway.
                    Budget estimate     Rs. 50,000
                   Actual expenditure   „    11,383
             The whole road was resurfaced and the stone parapets were completed on each
        side to the end of the road.
              i.   Police Family Quarters,
                   Budget estimate      Rs. 20,000
                   Actual expenditure   .,   29,440
             The provision for this work was inadequate as the buildings were constructed
        of cement concrete instead of local style ferrush stone. The expenditure includes
       cost of a cement drain running the length of the married lines to carry off water into
        the water channel which flows from the Fort garden to the sea on the south of the
       Fort.
             J. Water Tower of Fort.
                   Budget estimate      Rs. 3,500
                   Actual expenditure    „   4,170
             This work was carried out by the Electric Department and includes a small
       tank and a water supply to the married lines and the Fort. The expenditure is to
       be adjusted in the Public Works Department account for 1358.

             If. Muharraq Sea Road Extension.
                   Budget estimate      Rs. 40,000
                   Actual expenditure    „   40,000
             This sum was paid to the Muharraq Municipality as a special grant to assist
       the municipality to extend the sea road as far as the sohool on the northern edge
       of the town.

             1- Major Repairs to Quarantine.
                   Budget estimate      Rs. 7,500
                   Actual expenditure    „   7,938
             The Quarantine buildings were thoroughly repaired and new kitchens and
       latrines were constructed and a pier was built.
             W. Fort Wall and Tower.
                   Budget estimate      Rs. 25,000
                   Actual expenditure    „ 16,000
   152   153   154   155   156   157   158   159   160   161   162