Page 191 - Bahrain Gov Annual Reports (II)_Neat
P. 191

36
             Electricity Department-New Load for 1358
             1. It is understood that the Tt.A.F. intends to build hangars, etc., for one
       flight, (togethor with a small workshop, offices, quarters, etc.) near their landing
       ground at Muharraq, and to take a supply of electricity from the Government mains
       in bulk.
         . It is proposed to erect a substation at their site which will be fed from the
       H.T. substation in Muharraq Town by means of a fl.T. cable. The connected load
       is estimated to bo approximately 40 k.w.
            2.  The Government proposes to build a swing bridge across the channel,
       between Manama and Muharraq. This will be driven by electricity.
            3.  Messrs. Cable & Wireless propose to eliminate their battery at the old
      Wireless Station, which will be added to their connected load, approximately 10 k.w.
            4.  The Government Hospital, when completed, will take approximately
       35 k.w.
            5. It is estimated, provided that prospective consumers take the load they
       have applied for, (and assuming that approximately 50 k.w. is added in the normal
       way) that by the end of the year 1358 a further 125-50 k.w. of connected load will
       be connected.
            The question of generating capacity will then have to be considered with
      view to enlarging the Government Station to cope with future load.
   186   187   188   189   190   191   192   193   194   195   196