City of Encinitas                          Permit and Service Delivery — Performance Standards + Process Guide



     TI O N 8  Level 2  Complex Ministerial Permits, Decisions or Services




     E C         Decision-Maker      Staff or Deputy Director

     S
                 Appeal                Deputy Director or City Council for permits decided upon by the Deputy Director


                 Type                Permits
                                     •   Building permit: complex or large commercial or industrial projects (per
                                      EsGil contract)
                                     •  Building permit: complex or large mixed use projects (per EsGil contract)
                                     •  Building permit: complex or large multifamily projects (per EsGil contract)
                                     •  Building permit: complex or large single family attached residential
                                      projects (per EsGil contract)
                                     •  Building permit: complex or large single family detached residential
                                      projects (per EsGil contract)
                                     •  Boundary (Lot Line) Adjustment
                                     •   Certificate of Compliance

                                     •  Final Parcel Map
                                     •  Final Subdivision Map
                                     •  Grading (environmental review may be required)
                                     •  Sidewalk dining permit (right-of-way encroachment permit)


                                     Decisions
                                     •  Affordable Unit Policy
                                     •  Public Convenience or Necessity finding for off-sale alcohol
                                     •  Substantial Conformance Review—complex


                                     Services
                                     •  None

                 Timeline            2–8 months


                                                                  TOTAL CITY AND APPLICANT

                                     ROUNDS OF REVIEW             PROCESSING TIME
                                     One Cycle Review             2 months
                                     Two Cycle Reviews            4 months
                                     Three Cycle Reviews          6 months
                                     Four Cycle Reviews           8 months