City of Encinitas Permit and Service Delivery — Performance Standards + Process Guide
TI O N 8 Level 2 Complex Ministerial Permits, Decisions or Services
E C Decision-Maker Staff or Deputy Director
S
Appeal Deputy Director or City Council for permits decided upon by the Deputy Director
Type Permits
• Building permit: complex or large commercial or industrial projects (per
EsGil contract)
• Building permit: complex or large mixed use projects (per EsGil contract)
• Building permit: complex or large multifamily projects (per EsGil contract)
• Building permit: complex or large single family attached residential
projects (per EsGil contract)
• Building permit: complex or large single family detached residential
projects (per EsGil contract)
• Boundary (Lot Line) Adjustment
• Certificate of Compliance
• Final Parcel Map
• Final Subdivision Map
• Grading (environmental review may be required)
• Sidewalk dining permit (right-of-way encroachment permit)
Decisions
• Affordable Unit Policy
• Public Convenience or Necessity finding for off-sale alcohol
• Substantial Conformance Review—complex
Services
• None
Timeline 2–8 months
TOTAL CITY AND APPLICANT
ROUNDS OF REVIEW PROCESSING TIME
One Cycle Review 2 months
Two Cycle Reviews 4 months
Three Cycle Reviews 6 months
Four Cycle Reviews 8 months