City of Encinitas Permit and Service Delivery — Performance Standards + Process Guide
TI O N 8 Level 3-NOD or Level 3-HRG
Administrative Discretionary Permits with or without a Hearing
E C
S Decision-Maker Deputy Director
Appeal City Council
Type • Coastal Development Permit—administrative
• Design Review—administrative
• Minor Use Permit—not alcohol-related
• Sign Program
• Parcel Map Waiver
• Tentative Parcel Map
• Variance—administrative
Timeline 4–9 months
5–14 months if not exempt from CEQA*
TOTAL CITY AND APPLICANT
ROUNDS OF REVIEW PROCESSING TIME
One Cycle Review 4 months
Two Cycle Reviews 6 months
Three Cycle Reviews 8 months
Four Cycle Reviews 9 months
Additional Time if Not +1–5 months
Exempt from CEQA*
(95% of Level 3 projects are exempt)
* Applicable to Mitigated/Negative Declarations and similar CEQA documents only. An M/ND that
does not extend beyond the permit cycle reviews and does not involve responses to significant
public comments will take about one month longer to process. An M/ND that takes the maximum
allotted review cycles and involves responses to significant public comments could take an
additional five months to process. Most M/NDs will be processed in between these minimum and
maximum additional times.