City of Encinitas Permit and Service Delivery — Performance Standards + Process Guide
TI O N 8 Level 1 Simple Ministerial Permits, Decisions or Services
E C Decision-Maker Staff or Deputy Director
S
Appeal Deputy Director or City Council for permits decided upon by the Deputy Director
Type Permits
• Building permit: non-complex apartments, condominiums and
commercial projects (per EsGil contract)
• Building permit: non-complex residential projects (per EsGil contract)
• Signs—simple permanent
• Simplified grading permit
Decisions
• Substantial Conformance Review—simple
Services
• Information inquiry—fee for service request (e.g., zoning letter—no
cycle reviews are required for service requests)
• Staff Advisory Committee (Pre-application meeting notes—Cycle 1
City time only)
Timeline 2–5 months
TOTAL CITY AND APPLICANT
ROUNDS OF REVIEW PROCESSING TIME
One Cycle Review 2 months
Two Cycle Reviews 3 months
Three Cycle Reviews 4 months
Four Cycle Reviews 5 months