POC – Point of grid connection
Grid provider (DSP/TSO,...) defines the (POC) point
of grid connection during „connection procedure“
Information must be provided from the customers
about the requirements/agreements with the grid operator!
Project-specific, no general statement possible!
POC is important for determination of the voltage
level (eg. 400V, 20KV, 35KV, 60KV, 110KV, 220KV)