9.  Passenger Amenities Works profile                 :
        Works in progress     :
                                                                                                        Amount
          S.No                               Description                                Year of Sanc       in
                                                                                                         crores
                 Guntur - Foot over bridge connecting all platforms, east & west         2015-2016       10.42
            1    circulating areas

            2    GNT Divn: Construction of platform no 8 at Guntur                       2015-2016       1.98
                 GNT Division: Provision of coach watering and drainage arrangements     2015-2016       1.99
            3    duly cutting the edge of PF No 7 to facilitate PF no 8 at Guntur.

            4    Improvements to west side circulating area   at Guntur station          2015-2016       1.80
                 GNT - Construction of RCC shelter on Platform no 8 In front of new      2015-2016       1.54
            5    station building at Guntur

                 GNT - Construction of New station building  On west side of Guntur      2015-2016       1.52
            6    station
                 Guntur division: GUNTUR-Provision of Escalators-2 Nos for Guntur        2016-2017       1.60
            7    Railway station New Foot over bridge.

                 Guntur Division: Provision of divyang facilities at D, E, F category    2017-2018       0.50
            8    stations
                 Improvements to SS/Dy. SS rooms, Booking Office for better PAs at       2018-2019       0.75
            9    Ground floor and better commercial exploitation.

                 GUNTUR~~Provision of Echo friendly self paid wash rooms including       2018-2019       0.80
           10    Divyang toilet facilities.

                 GUNTUR~~Provision of more hygienic and convenient drinking water        2018-2019       0.40
           11    facilities to Guntur station.
                 Replacement of Coach Indication Boards and At a  Glance boards on       2018-2019       1.00
           12    PF No: 1,3,5&6 at Guntur station under Guntur Redevelopment

                 Re-location of Parcel Office to end of PF-1 to avoid inconvenience to   2018-2019       0.64
           13    passengers.

           14    Improvements of station lighting of Guntur station.                     2018-2019       0.61

           15    Guntur division: Guntur Provision of 2 Nos of Passenger Lifts for FOB   2018-2019       1.07
                 at Guntur Railway station.
                 Providing water supply arrangements to passengers at various            2018-2019       2.52
           16    stations in GNT Division.
                 Basic amenities at CTYL, DKD, JNPD, NLDA, NRT, PDGA, REP &              2018-2019       0.81
           17    VNUP goods sheds over Guntur division.
                 GUNTUR~~GNT Division-Provision of additional Pre-cooling points         2018-2019       0.28
                 and Battery charging Points at various Railway stations  over GNT
           18
                 division.
                 GUNTUR~~GNT Division: Provision of 04 Nos of passenger Lifts at         2019-2020       2.17
                 Guntur Railway station.
           19


                     New works sanctioned and yet to be taken up:
                                                                                                       Amount
            S.No                              Description                               Year of San       in
                                                                                                        crores
                   GUNTUR~~Provision of Granite flooring in front of West side new       2018-2019       0.74
           1       station building at Guntur.
                   Uplifting of West side facade station building for aesthetic          2018-2019       2.00
           2
                   elevation.
                   Multi level Parking complex on both sides of Station building for     2018-2019       2.00
           3       both long & short duration parking for 2 & 4 wheelers.
                   Provision of PA system at 27 stations of NSG1 to NSG-6 over           2019-2020       1.65
           4
                   Guntur division