Page 107 - E-BOOKLET VERSION OF 2020-21 CCM Total Booklet with profiles
P. 107
9. Passenger Amenities Works profile :
Works in progress :
Amount
S.No Description Year of Sanc in
crores
Guntur - Foot over bridge connecting all platforms, east & west 2015-2016 10.42
1 circulating areas
2 GNT Divn: Construction of platform no 8 at Guntur 2015-2016 1.98
GNT Division: Provision of coach watering and drainage arrangements 2015-2016 1.99
3 duly cutting the edge of PF No 7 to facilitate PF no 8 at Guntur.
4 Improvements to west side circulating area at Guntur station 2015-2016 1.80
GNT - Construction of RCC shelter on Platform no 8 In front of new 2015-2016 1.54
5 station building at Guntur
GNT - Construction of New station building On west side of Guntur 2015-2016 1.52
6 station
Guntur division: GUNTUR-Provision of Escalators-2 Nos for Guntur 2016-2017 1.60
7 Railway station New Foot over bridge.
Guntur Division: Provision of divyang facilities at D, E, F category 2017-2018 0.50
8 stations
Improvements to SS/Dy. SS rooms, Booking Office for better PAs at 2018-2019 0.75
9 Ground floor and better commercial exploitation.
GUNTUR~~Provision of Echo friendly self paid wash rooms including 2018-2019 0.80
10 Divyang toilet facilities.
GUNTUR~~Provision of more hygienic and convenient drinking water 2018-2019 0.40
11 facilities to Guntur station.
Replacement of Coach Indication Boards and At a Glance boards on 2018-2019 1.00
12 PF No: 1,3,5&6 at Guntur station under Guntur Redevelopment
Re-location of Parcel Office to end of PF-1 to avoid inconvenience to 2018-2019 0.64
13 passengers.
14 Improvements of station lighting of Guntur station. 2018-2019 0.61
15 Guntur division: Guntur Provision of 2 Nos of Passenger Lifts for FOB 2018-2019 1.07
at Guntur Railway station.
Providing water supply arrangements to passengers at various 2018-2019 2.52
16 stations in GNT Division.
Basic amenities at CTYL, DKD, JNPD, NLDA, NRT, PDGA, REP & 2018-2019 0.81
17 VNUP goods sheds over Guntur division.
GUNTUR~~GNT Division-Provision of additional Pre-cooling points 2018-2019 0.28
and Battery charging Points at various Railway stations over GNT
18
division.
GUNTUR~~GNT Division: Provision of 04 Nos of passenger Lifts at 2019-2020 2.17
Guntur Railway station.
19
New works sanctioned and yet to be taken up:
Amount
S.No Description Year of San in
crores
GUNTUR~~Provision of Granite flooring in front of West side new 2018-2019 0.74
1 station building at Guntur.
Uplifting of West side facade station building for aesthetic 2018-2019 2.00
2
elevation.
Multi level Parking complex on both sides of Station building for 2018-2019 2.00
3 both long & short duration parking for 2 & 4 wheelers.
Provision of PA system at 27 stations of NSG1 to NSG-6 over 2019-2020 1.65
4
Guntur division
119