Page 3 - Barr&Barr_Cost Proposal
P. 3
GUARANTEED MAXIMUM COST CONTRACT
CORNELL TECH CAMPUS
VERIZON EXECUTIVE EDUCATION CENTER
EARLY WORK PACKAGE 1 (EXCAVATION AND FOUNDATION) AND
CONSTRUCTION MANAGEMENT COST
PROPOSAL FORM
Name of Bidder: Barr & Barr, Inc.
Address: 460 West 34th Street
New York, NY 10001
Telephone Number: 212/563-2330
TO: Cornell University
Facilities Contracts
121 Humphreys Service Building
Ithaca, New York 14853-3701
Attn: Nancy A. Phelps, Director
1. GUARANTEED MAXIMUM COST
The Construction Manager shall submit their costs associated with the construction of the
complete Verizon Executive Education Center building, a four-story 40,000 gsf steel frame
building which is anticipated to have a total GMC cost in the range of $31,000,000 to
$33,000,000:
a) Cost of Work / Trade Cost (Package 1)
b) General Conditions (Cost Proposed for Entire Project)
c) CM Fee (Percentage of Cost of Work and General Conditions)
d) Bonding / Subguard (Percentage of Trade Cost)
e) Insurance (Percentage of Trade Cost and General Conditions)
f) Contingency (Percentage of Trade Cost)
Addendum No. 3 COST PROPOSAL FORM BF-1