Page 24 - Barr&Barr_HealthcarePortfolio.indd
P. 24

Trinitas Hospital

                                                 4th Floor Oncology Care Center


































          SIZE                     OWNER
          14,000 square feet       Trinitas Regional
                                   Medical Center
          CONTRACT TYPE
          Construction Manager-at-Risk  ARCHITECT
                                   Pallante Design






                                                                       PROJECT DETAILS

          Originally constructed in 1964 as a med/surg unit the time had arrived       •   Th  e project required the total gut demolition of
          to convert the fl oor for cancer care.                            the space while at the same time not disturbing
                                                                            the services of the renal dialysis and endoscopy
                                                                            centers on the fl oor immediately below.
                                                                          •   Detailed phasing scenarios incorporating “after
                                                                            hours” shift work  accommodated the installation
                                                                            of the new mechanical, electrical and plumbing
                                                                            systems.
                                                                          •   High end fi nishes throughout the project have
                                                                            created a warm, caring environment for the
                                                                            patients.
   19   20   21   22   23   24   25   26