Bridgewater State University

                                        Science and Mathematics Building, Bridgewater, MA





















         SIZE                                CONSTRUCTION COST ESTIMATES
         213,000 square feet                 SD $83M
                                             DD $82.4M
         CONTRACT TYPE
         Construction Manager-at-Risk        ACTUAL BID PRICING
                                             $77M
         OWNER
         Bridgewater State University        LEED CERTIFICATION
         (DCAMM Project)                     LEED Silver Certifi cation
         REFERENCE
         Karen Jason, Facilities Director
         508.531.1000







                                                                  PROJECT DETAILS
        Th  is project consisted of the renovation of 43,000 SF and 19,000   •  Massachusetts Division of Capital Asset Management &
        SF addition to the Marshall Conant Science Building along with   Maintenance (DCAMM) funded project.
        construction of new 151,000 SF Science Building. Th e major   •  Th  e largest building project in the University’s history
        modernization of the University’s science facilities included the   in addition to the largest capital improvement project in
        renovation of the existing Marshall Conant Science Building and the   DCAMM’s history.
        construction of a major addition to accommodate science/teaching   •  OSHA Partnership with the U.S. Labor Department to
        laboratories, classrooms, offi  ces and support space for the Biology,   emphasize employee training and an ongoing commitment
        Chemical Sciences, Earth Sciences, Geography, Math, Computer   to identifying and eliminating hazards before they harm
                                                                       workers.
        Science and Physics Departments.
                                                                      •  A high standard of sustainability was met through the use
                                                                       of recycled and locally extracted and manufactured materials,
        Barr & Barr provided preconstruction services for this project during   low-VOC building products, low-mercury fl uorescent
        the extremely volatile market of 2008 – 2010. Th  rough our rigorous   lighting, public transportation access, bike racks, storm water
        preconstruction eff orts, Barr & Barr was able to value manage   collection, solar thermal hot water, natural daylight and a
        project scope to bring down the original budget. One of these items   green roof. LEED Silver certifi cation.
        was working closely with the architect to adjust the design of the   •  Minimized disruptions to students and faculty occupying
        buildings atrium so it would not require a smoke evacuation system;   adjacent academic buildings, residence halls, and the main
        this alone reduced the original project budget signifi cantly.   One   quad.
        of the logistical challenges that our team addressed was the active   •  Aggressive scheduling in order to coordinate and
        primary electrical feeds for several buildings  as well as active steam   synchronize with University’s academic schedule.
        mains had to remain live within the footprint of the building during   •  Building Informational Modeling was employed for certain
        construction until fi nal transfer 2 years later.  Th  is required our team   aspects of coordination and glazing interface with structural
        developing a means and method process that was quantifi able so hard   components.
        bids could be established for this work.
                                                                      •  Program included more than 85 labs, 18 general purpose
                                                                       classrooms, an observatory and a rooftop botanical garden.
        Th  is critical time “ Th e fi nancial crash of 2009” also required complete   •  Th  is building and project has enabled the State to be a
        vetting of subcontractors closely evaluating fi nancial strength, back   competitive entity within higher learning undergraduate
        log and manpower availability.  Th  e subcontractors selected for   community for private and public Universities.
        this project ensured the GMP was  protected as well as the critical
        scheduled completion date was met.