Page 7 - Newsletter_November2017
P. 7

Step 9:                                           Step 10:

                                    Notice the train going by.  The                   That’s as far as the jacks will go…
                                    railroad had flaggers on the tracks,
                                    and train speed was reduced, but
                                    the work continued below.





                                    Step 11:                                          Step 12:

                                    Blocks added.  In this photo they                 Breakthrough! Once the pipe
                                    have about a foot to go, then they                reached the sheet piles on the
                                    remove the blocks and lower                       other side a torch was used to cut
                                    another section of pipe.                          around the pipe and the jacking
                                                                                      was complete.




                                    Step 13:                                          Step 14:

                                    Grout was pumped through three                    Conduit supports were required
                                    ports in each pipe section to fill                every 10-feet.  The unistrut was
                                    any voids outside the pipe.  After                put together on site and equipped
                                    some touch-up painting the work                   with rollers so that no further
                                    inside the pipe was complete.                     pipe entry was necessary.




                                    Step 15:                                          Step 16:

                                    Electricians fastening conduits                   Once all the conduit was in, flow
                                    to unistrut support.                              fill was pumped into the pipe to
                                                                                      fill all the voids and backfilling
                                                                                      of the pit and shoring removal
                                                                                      began.









          Lesson Learned:
          This operation was well-planned and went very smoothly.  As the pipe jacking subcontractor was setting up, we noticed that the
          blower to be used to provide fresh air to the pipe was within 5-10 feet of several pieces of gasoline/diesel powered equipment (a
          generator, portable lighting plant, air compressor, and the power pack for the hydraulic jacks).  We were worried that the exhaust
          from the equipment might reach the fan intake and be forced into the pipe, and asked them to move the blower or the fuel-powered
          equipment.  They decided to move the blower approximately 20-feet away and started the operation uneventfully.  At about the
          midway point the wind picked up a little, and the tunnel worker in the pipe noticed an exhaust-type odor and the air monitor reading
          low levels of carbon monoxide.  The equipment up above was moved about another 20-feet from the pit and the issue was resolved.

          Although it is unlikely that we will encounter much pipe jacking in our future, this example would be applicable to any confined
          space entry work we do where a blower is used to force fresh air into the space.  There have been countless examples over the years
          where equipment was started or vehicles pulled up near the fan intake and dangerous conditions resulted inside the confined space.
          It is important that the attendant for any confined space pay attention and protect the quality of the air being pumped into the space!
   2   3   4   5   6   7   8   9   10   11   12