Page 4 - KOP Panborneo Highway Report Card Jan-june 2017
P. 4
Overview
This report provides the progresive update of the Project Porfolio :
Kick Off Project (KOP) Panborneo Highway from
1st January 2017 to 30th June 2017.
Employer : Government of Malaysia
The Kick Off Project is the first Package under the Project Director : Regional Manager,
upgrading of Existing Single Carriage Way Northern Region Office,
Panborneo Road in Sarawak to Dual Carriage Way JKR, Sarawak
R5 Standard Highway from Nyabau Juction, Bintulu Main Contractor : Lebuhraya Borneo Utara S/B
to Bakun Junction (42.9 KM). C&S Consultant : Jurutera Minsar Consult S/B
M&E Consultant : Konsortium Bumi
The KOP Panborneo Highway Highway project Consultants & Services
serves as the pioneer project for the whole
upgrading of the Panborneo Highway and plays an Traffic Management : T&D Consult S/B
important role to determine the typical issues and Environmental Consultant : Chemsain Konsultant S/B
challenges encountered during implementation Original Contract Sum : RM 637,752,765.70
th
w h i c h i s b e n e f i c i a l f o r t h e s u c c e s s f u l Letter Of Acceptance Date : 30 March 2015
th
implementation of other packages. Contract Commencement Date : 30 April 2015
Contract Period : 30 Months
This upgrading works is also another commitment by Revised Contract Period : 33 Months (EOT No.1)
the Malaysian Government to continue serving the Revised Contract Period : 40 Months (EOT No.2)
th
needs of the travelling public and achieve Original Contract Completion Date : 29 October 2017
transportation efficiency , while ensuring the safety Revised Contract Completion Date : 6 February 2018 (EOT No.1)
th
of the Public once the project completed. The Revised Contract Completion Date : 20 August 2018 (EOT No.2)
th
Project also meets the needs of the communities Defect Liability Period : 24 Month
living along the Highway.