Page 4 - KOP Panborneo Highway Report Card Jan-june 2017
P. 4

Overview





             This report provides the progresive update of the                   Project Porfolio :
             Kick Off Project (KOP) Panborneo Highway from
             1st January 2017 to 30th June 2017.
                                                                                 Employer                           : Government of Malaysia
             The Kick Off Project is the first Package under the                 Project Director                   : Regional Manager,
             upgrading of Existing Single Carriage Way                                                                Northern Region Office,
             Panborneo Road in Sarawak to Dual Carriage Way                                                           JKR, Sarawak
             R5 Standard Highway from Nyabau Juction, Bintulu                    Main Contractor                    : Lebuhraya Borneo Utara S/B
             to Bakun Junction (42.9 KM).                                        C&S Consultant                     : Jurutera Minsar Consult S/B

                                                                                 M&E Consultant                     : Konsortium Bumi
             The KOP Panborneo Highway Highway project                                                                Consultants &  Services
             serves as the pioneer project for the whole
             upgrading of the Panborneo Highway and plays an                     Traffic Management                 : T&D Consult S/B
             important role to determine the typical issues and                  Environmental Consultant           : Chemsain Konsultant S/B
             challenges encountered during implementation                        Original Contract Sum              : RM 637,752,765.70
                                                                                                                      th
             w h i c h   i s   b e n e f i c i a l   f o r   t h e   s u c c e s s f u l   Letter Of Acceptance Date    : 30  March 2015
                                                                                                                      th
             implementation of other packages.                                   Contract Commencement Date         : 30  April 2015
                                                                                 Contract Period                    : 30 Months
             This upgrading works is also another commitment by                  Revised Contract Period            : 33 Months (EOT No.1)
             the Malaysian Government to continue serving the                    Revised Contract Period            : 40 Months (EOT No.2)
                                                                                                                      th
             needs of the travelling public and achieve                          Original Contract Completion Date : 29  October 2017
             transportation efficiency , while ensuring the safety               Revised Contract Completion Date : 6  February 2018 (EOT No.1)
                                                                                                                     th
             of the Public once the project completed. The                       Revised Contract Completion Date : 20  August 2018 (EOT No.2)
                                                                                                                      th
             Project also meets the needs of the communities                     Defect Liability Period            : 24 Month
             living along the Highway.