Page 6 - KOP Panborneo Highway Report Card Jan-june 2017
P. 6
Scope of Works
26 nos. Bus Sheds 12 nos. P-Turns 539 nos. SESCO H T Poles
432 nos. SESCO L t Poles
31 KM Guardrails (Single) 2 nos. Pedestrian Bridges 2 nos. Minor Junctons 247 nos. SACOFA Manhole
39KM Guardrails (Double) 258 nos. TELEKOM Manhole
80 nos. Culvert (Major) 4 nos. Bridges 1 no. Signalized Junction
44 nos. Culvert (Surface)
3 199 nos. Culvert (Minor)