Page 9 - KOP Panborneo Highway Report Card Jan-june 2017
P. 9

progress status OVERVIEW















                             Physical progress                                                     financial progress


                                             2.24%                                                                   1.66%


                                             ahead of schedule                                                       ahead of schedule



                      contractor's earned value                                         payment received by contractor










                  monthly average safety manhr                                               cumulative safety manhr











                                                                                                                                                 6
   4   5   6   7   8   9   10   11   12   13   14