Page 52 - KOP Panborneo Highway Report Card Jan-june 2017
P. 52

Quality assurance & control                                                                   progress summary






                                                                                           Cumulative           Cumulative
                  Item        Description of Item                                                                                   Variance
                                                                                           Scheduled                Actual



                   (A)        EARTHWORKS                                                     49.91%               50.03%              0.12%


                   (B)        ROAD PAVEMENT                                                  11.01%               23.28%             12.27%


                   (C)        TESTS FOR PILES                                                 100%                60.18%            -39.82%


                   (D)        TESTS FOR CONCRETE WORKS                                         75%                79.53%             4.53%



                   (E)        ELASTROMETRIC BEARING FOR ALL BRIDGES                           100%                100.00%            0.00%


                   (F)        SOIL TREATMENT & STABILIZATION                                 35.22%               36.62%             1.40%


                   (G)        REINFORCING STRUCTURAL STEEL BARS                              66.66%               33.33%            -33.33%


                   (H)        RELOCATION OF WATER PIPELINES                                  44.15%               46.91%             2.76%