Quality assurance & control progress summary
Cumulative Cumulative
Item Description of Item Variance
Scheduled Actual
(A) EARTHWORKS 49.91% 50.03% 0.12%
(B) ROAD PAVEMENT 11.01% 23.28% 12.27%
(C) TESTS FOR PILES 100% 60.18% -39.82%
(D) TESTS FOR CONCRETE WORKS 75% 79.53% 4.53%
(E) ELASTROMETRIC BEARING FOR ALL BRIDGES 100% 100.00% 0.00%
(F) SOIL TREATMENT & STABILIZATION 35.22% 36.62% 1.40%
(G) REINFORCING STRUCTURAL STEEL BARS 66.66% 33.33% -33.33%
(H) RELOCATION OF WATER PIPELINES 44.15% 46.91% 2.76%