Page 69 - KOP Panborneo Highway Report Card Jan-june 2017
P. 69

utilities relocation works overview







                Description of Item                scheduled                   Actual              Variance




                  Overall                       49.46%                    47.63% -1.83%


                   URW Progress


































                                                                                                                                                66