Page 70 - KOP Panborneo Highway Report Card Jan-june 2017
P. 70
utilities relocation works progress summary
Items Status Remarks scheduled actual
M&E Works 0% 0%
Street Lighting Works Pending Bridge completion and road pavement completion. 0% 0%
Traffic Lights Pending Junction Completion. 0% 0%
Relocation of Utility Services 49.46% 47.63%
SESCO CH8+400 – CH42+966 permanent relocation has been energized. 95.33% 85.93%
Pole erection and conductor sagging activities at CH0+000 –
CH8+400 in progress. Tentative testing date for CH5+000 –
CH8+400 is early 25 July 2017