Page 70 - KOP Panborneo Highway Report Card Jan-june 2017
P. 70

utilities relocation works                                                                    progress summary






                       Items                                           Status Remarks                                   scheduled      actual


              M&E Works                                                                                                     0%            0%


            Street Lighting Works              Pending  Bridge completion and road pavement completion.                    0%            0%


            Traffic Lights                     Pending Junction Completion.                                                0%            0%


              Relocation of Utility Services                                                                              49.46%        47.63%


            SESCO                              CH8+400 – CH42+966 permanent relocation has been energized.              95.33%        85.93%
                                               Pole erection and conductor sagging activities at CH0+000 –

                                                CH8+400 in progress. Tentative testing date for CH5+000 –

                                                CH8+400 is early 25  July 2017
                                                                     th
















          67