Page 71 - KOP Panborneo Highway Report Card Jan-june 2017
P. 71

utilities relocation works                                                                    progress summary






            Items                                               Status Remarks                                          scheduled      actual



              Relocation of Utility Services                                                                              49.46%        47.63%

            SACOFA               Installation of manhole and pipe trenching works at CH19+000 – CH22+000,               17.49%        22.44%

                                  CH31+000 – CH32+000, and CH35+000 – CH42+966 ongoing.

                                 Temporary relocation CH6+700 – CH8+400 and CH17+000– CH42+966 completed.
                                 Permanent Underground Fiber Optic Cable at CH40+000 – CH42+966 tested.


            TELEKOM              Installation of manhole and pipe trenching works at CH19+000 – CH22+000,               15.86%        21.74%
                                  CH31+000 – CH32+000, and CH35+000 – CH42+966 ongoing.

                                 Temporary relocation CH6+700 – CH8+400 and CH17+000– CH42+966 completed.

            LAKU/JKR             Permanent Pipe jointing completed at CH18+637 – CH18+875, CH19+200 –                   22.75%        30.23%

                                  CH19+275, CH20+000 – CH24+700 and CH28+000 – CH42+966
                                 Pressure test completed at CH21+200 – CH42+966