Page 71 - KOP Panborneo Highway Report Card Jan-june 2017
        P. 71
     utilities relocation works                                                                    progress summary
            Items                                               Status Remarks                                          scheduled      actual
              Relocation of Utility Services                                                                              49.46%        47.63%
            SACOFA               Installation of manhole and pipe trenching works at CH19+000 – CH22+000,               17.49%        22.44%
                                  CH31+000 – CH32+000, and CH35+000 – CH42+966 ongoing.
                                 Temporary relocation CH6+700 – CH8+400 and CH17+000– CH42+966 completed.
                                 Permanent Underground Fiber Optic Cable at CH40+000 – CH42+966 tested.
            TELEKOM              Installation of manhole and pipe trenching works at CH19+000 – CH22+000,               15.86%        21.74%
                                  CH31+000 – CH32+000, and CH35+000 – CH42+966 ongoing.
                                 Temporary relocation CH6+700 – CH8+400 and CH17+000– CH42+966 completed.
            LAKU/JKR             Permanent Pipe jointing completed at CH18+637 – CH18+875, CH19+200 –                   22.75%        30.23%
                                  CH19+275, CH20+000 – CH24+700 and CH28+000 – CH42+966
                                 Pressure test completed at CH21+200 – CH42+966
                                                                                                                                                68





