Page 71 - KOP Panborneo Highway Report Card Jan-june 2017
P. 71
utilities relocation works progress summary
Items Status Remarks scheduled actual
Relocation of Utility Services 49.46% 47.63%
SACOFA Installation of manhole and pipe trenching works at CH19+000 – CH22+000, 17.49% 22.44%
CH31+000 – CH32+000, and CH35+000 – CH42+966 ongoing.
Temporary relocation CH6+700 – CH8+400 and CH17+000– CH42+966 completed.
Permanent Underground Fiber Optic Cable at CH40+000 – CH42+966 tested.
TELEKOM Installation of manhole and pipe trenching works at CH19+000 – CH22+000, 15.86% 21.74%
CH31+000 – CH32+000, and CH35+000 – CH42+966 ongoing.
Temporary relocation CH6+700 – CH8+400 and CH17+000– CH42+966 completed.
LAKU/JKR Permanent Pipe jointing completed at CH18+637 – CH18+875, CH19+200 – 22.75% 30.23%
CH19+275, CH20+000 – CH24+700 and CH28+000 – CH42+966
Pressure test completed at CH21+200 – CH42+966