Page 2 - Microsoft Word - TECHNICAL SPECIFICATION- APOLLO HOSPITALS TEYNAMPET
P. 2

Document Name: TECHNICAL SPECIFICATION                                            DOCUMENT NO.:  ESCP-AUDOC-TESP-002


                          AUTOMATED MULTI LEVEL CAR PARKING SYSTEM – 102 cars



                         PROPOSED MLCP AT APOLLO HOSPITALS - TEYNAMPET

                                         TECHNICAL SPECIFICATION


             PREFACE

             The Automated Multi Level Car Parking System considered by E STAR Engineers Pvt. Limited is
             to facilitated to accommodate maximum no. of cars in the limited space available.
             This entire system is fully automated, and is operated and controlled by a Programmable Logic
             Control  System  (PLC)  of  Reputed  make,  and  the  entire  program  is  developed  by  E  STAR
             Engineers private Limited. This program is designed   to suit the various system of Parking like
             Tower Parking, SS (Shuttle Stacker) Tower Parking, Puzzle Parking Etc. with estimated shortest
             retrieval time of 180 seconds.

                     The system is designed for the easy operation by any technical person with utmost
             care taken in quality, Safety of Vehicles and as well as human.
             The System considered is fully automatic and operated by Human Machine Interface System
             (HMI).

             Utmost care has considered in the System for avoiding Dent, Scratches or any kind of Damages to
             the vehicles.

             SCOPE OF WORK

                                 E STAR ‘S SCOPE:

                                     1.  Design,  Manufacture,  Erection  and  Commissioning  of  Car  Parking
                                        system of 102 Cars (G+6 Levels) SS Parking – Front –Back Parking.
                                     2.  Preparation of GA Drawings for client Approval
                                     3.  Preparation of Drawings for CMDA Approval
                                 CLIENT’S SCOPE:
                                     1.  Getting Approval from CMDA
                                     2.  Civil Foundations and Cladding
                                     3.  Firefighting system for MLCP
                                     4.  Electrical Lighting & Routing for MLCP
                                     5.  To Provide 3 Phase Power supply for MLCP
                                     6.  To Provide additional Generator Power Backup for MLCP