Page 230 - Facilities Master Plan 2016
P. 230
SCOPE OF WORK CATEGORIES COST
1. Modernize & Reconfigure Existing Classrooms $ 253,000
2. Existing Building Systems & Toilets $ 612,000
3. Site Utilities --
4. Classrooms - New Construction $ 6,759,000
5. Maker Spaces & Science Labs $ 980,000
6. Electives --
7. Performing Arts Improvements $ 998,000
8. MPR/Food Service Improvements & Student Dining $ 545,000
9. Physical Education Improvements $ 1,241,000
10. Administration & Staff Support $ 234,000
11. Library & Student Support Services $ 614,000
12. Safety, Security, & Campus Control $ 1,271,000
13. District Support Facilities --
14. Outdoor Learning Environment & Quads $ 110,000
15. Exterior Play Spaces, Playfields, & Hardcourts $ 1,027,000
16. Next Generation Classroom Flexibility (Furniture) $ 248,000 The following items are
excluded from this budget:
17. Technology Infrastructure -- • Utility hook-up fees & City connection fees
• Off-site work and traffic signals
• Land acquisition costs
Total Project Cost ($2016) $ 14,892,000 • Hazardous material surveys
• Abatement and disposal
• Escalation (costs are in 2016$)
5.31 COST SUMMARY ($2016) Facilities Master Plan 228
ELLERTH E. LARSON ES Lodi Unified School District