Page 368 - Facilities Master Plan 2016
P. 368
SCOPE OF WORK CATEGORIES COST
1. Modernize & Reconfigure Existing Classrooms $ 876,000
2. Existing Building Systems & Toilets $ 1,053,000
3. Site Utilities $ 1,233,000
4. Classrooms - New Construction $ 8,963,000
5. Maker Spaces & Science Labs $ 1,577,000
6. Electives $ 984,000
7. Performing Arts Improvements $ 310,000
8. MPR/Food Service Improvements & Student Dining $ 1,447,000
9. Physical Education Improvements $ 9,188,000
10. Administration & Staff Support $ 1,226,000
11. Library & Student Support Services $ 2,204,000
12. Safety, Security, & Campus Control $ 2,446,000
13. District Support Facilities --
14. Outdoor Learning Environment & Quads $ 476,000
15. Exterior Play Spaces, Playfields, & Hardcourts $ 1,526,000
16. Next Generation Classroom Flexibility (Furniture) $ 195,000 The following items are
excluded from this budget:
17. Technology Infrastructure $ 32,000 • Utility hook-up fees & City connection fees
• Off-site work and traffic signals
• Land acquisition costs
Total Project Cost ($2016) $ 33,736,000 • Hazardous material surveys
• Abatement and disposal
• Escalation (costs are in 2016$)
5.52 COST SUMMARY ($2016) Facilities Master Plan 354
DELTA SIERRA MS Lodi Unified School District