Page 43 - Facilities Master Plan 2016
P. 43

Scope Category                             School Site
                                                     Elkhorn      Heritage Primary    Houston         Lakewood      Ellerth E. Larson   Lawrence
                                                     School         Elementary       Elementary      Elementary       Elementary      Elementary
         1.   Modernize & Reconfigure Existing Classrooms   648,000       2,006,000        2,088,000       2,809,000         253,000         827,000
         2.   Existing Building Systems & Toilets          601,000        1,535,000        1,455,000       1,749,000         612,000         360,000
         3.   Site Utilities                              1,583,000        708,000         1,321,000       1,619,000             --         1,909,000
         4.   Classrooms - New Construction               5,760,000      13,642,000         394,000       11,752,000        6,759,000       6,111,000
         5.   Maker Spaces & Science Labs                 3,477,000       1,958,000         650,000         827,000          980,000        1,647,000
         6.   Electives                                   2,304,000            --               --               --              --               --
         7.   Performing Arts Improvements                 998,000         998,000          998,000        1,248,000         998,000        1,134,000
         8.   MPR/Food Service Improvements & Student Dining   3,951,000    1,915,000      1,404,000       2,155,000         545,000        1,032,000
         9.   Physical Education Improvements             1,241,000       1,241,000        1,241,000       1,547,000        1,241,000       1,411,000
         10. Administration & Staff Support               1,442,000        846,000          388,000        1,299,000         234,000         633,000
         11. Library & Student Support Spaces             2,105,000       3,039,000         843,000        2,978,000         614,000        2,128,000
         12. Safety, Security, & Campus Control           1,061,000       1,720,000        1,901,000       2,636,000        1,271,000       1,089,000
         13. District Support Facilities                       --              --               --               --              --               --
         14. Outdoor Learning Environment & Quads          521,000         270,000          238,000         368,000          110,000         370,000
         15. Exterior Play Spaces, Playfields, & Hardcourts    1,786,000    571,000        1,496,000       2,351,000        1,027,000       1,381,000
         16. Next Generation Classroom Flexibility (Furniture)   60,000    255,000          210,000         240,000          248,000         345,000
         17. Technology Infrastructure                      64,000          32,000           32,000          32,000              --               --
                          Total Project Cost (2016$)  $   27,602,000   $   30,736,000   $   14,659,000   $   33,610,000   $   14,892,000   $   20,377,000

















         4.2       PROGRAM COSTS                                                                                               Facilities Master Plan  124
                   MASTER PLAN TOTAL COST SUMMARY                                                                          Lodi Unified School District
   38   39   40   41   42   43   44   45   46   47   48