Page 44 - Facilities Master Plan 2016
P. 44

Scope Category                             School Site
                                                     Live Oak        Lockeford      Julia Morgan   George L. Mosher   John Muir     Clyde W. Needham
                                                    Elementary      Elementary       Elementary      Elementary       Elementary      Elementary
         1.   Modernize & Reconfigure Existing Classrooms   722,000       1,153,000        2,942,000        108,000         2,615,000       3,060,000
         2.   Existing Building Systems & Toilets          863,000        1,029,000        2,528,000        612,000         2,774,000       1,623,000
         3.   Site Utilities                              1,225,000       2,451,000        1,592,000             --          807,000        1,724,000
         4.   Classrooms - New Construction               8,955,000       6,949,000        3,971,000       2,566,000        8,448,000       3,513,000
         5.   Maker Spaces & Science Labs                 1,958,000       1,958,000        2,225,000       1,394,000        1,958,000       1,641,000
         6.   Electives                                        --          454,000              --               --              --               --
         7.   Performing Arts Improvements                 998,000         998,000          998,000         998,000          998,000         621,000
         8.   MPR/Food Service Improvements & Student Dining   2,055,000    60,000         1,029,000        230,000         2,288,000       2,394,000
         9.   Physical Education Improvements             1,241,000            --          1,411,000       1,241,000        1,241,000       1,241,000
         10. Administration & Staff Support                704,000        2,371,000         626,000         234,000          549,000        1,073,000
         11. Library & Student Support Spaces             2,534,000       1,115,000        1,619,000        614,000         2,927,000       2,744,000
         12. Safety, Security, & Campus Control           1,761,000       1,017,000        1,214,000        299,000         1,279,000       1,936,000
         13. District Support Facilities                       --              --               --               --              --               --
         14. Outdoor Learning Environment & Quads          507,000         184,000          629,000          98,000           73,000         591,000
         15. Exterior Play Spaces, Playfields, & Hardcourts    1,389,000    1,093,000      1,984,000       1,045,000        1,385,000       1,354,000
         16. Next Generation Classroom Flexibility (Furniture)   120,000    195,000         345,000         248,000          375,000         750,000
         17. Technology Infrastructure                      32,000             --               --               --              --           64,000
                          Total Project Cost (2016$)  $   25,064,000    $   21,027,000   $   23,113,000   $     9,687,000   $   27,717,000   $   24,329,000

















         4.2       PROGRAM COSTS                                                                                               Facilities Master Plan  125
                   MASTER PLAN TOTAL COST SUMMARY                                                                          Lodi Unified School District
   39   40   41   42   43   44   45   46   47   48   49