Page 44 - Facilities Master Plan 2016
P. 44
Scope Category School Site
Live Oak Lockeford Julia Morgan George L. Mosher John Muir Clyde W. Needham
Elementary Elementary Elementary Elementary Elementary Elementary
1. Modernize & Reconfigure Existing Classrooms 722,000 1,153,000 2,942,000 108,000 2,615,000 3,060,000
2. Existing Building Systems & Toilets 863,000 1,029,000 2,528,000 612,000 2,774,000 1,623,000
3. Site Utilities 1,225,000 2,451,000 1,592,000 -- 807,000 1,724,000
4. Classrooms - New Construction 8,955,000 6,949,000 3,971,000 2,566,000 8,448,000 3,513,000
5. Maker Spaces & Science Labs 1,958,000 1,958,000 2,225,000 1,394,000 1,958,000 1,641,000
6. Electives -- 454,000 -- -- -- --
7. Performing Arts Improvements 998,000 998,000 998,000 998,000 998,000 621,000
8. MPR/Food Service Improvements & Student Dining 2,055,000 60,000 1,029,000 230,000 2,288,000 2,394,000
9. Physical Education Improvements 1,241,000 -- 1,411,000 1,241,000 1,241,000 1,241,000
10. Administration & Staff Support 704,000 2,371,000 626,000 234,000 549,000 1,073,000
11. Library & Student Support Spaces 2,534,000 1,115,000 1,619,000 614,000 2,927,000 2,744,000
12. Safety, Security, & Campus Control 1,761,000 1,017,000 1,214,000 299,000 1,279,000 1,936,000
13. District Support Facilities -- -- -- -- -- --
14. Outdoor Learning Environment & Quads 507,000 184,000 629,000 98,000 73,000 591,000
15. Exterior Play Spaces, Playfields, & Hardcourts 1,389,000 1,093,000 1,984,000 1,045,000 1,385,000 1,354,000
16. Next Generation Classroom Flexibility (Furniture) 120,000 195,000 345,000 248,000 375,000 750,000
17. Technology Infrastructure 32,000 -- -- -- -- 64,000
Total Project Cost (2016$) $ 25,064,000 $ 21,027,000 $ 23,113,000 $ 9,687,000 $ 27,717,000 $ 24,329,000
4.2 PROGRAM COSTS Facilities Master Plan 125
MASTER PLAN TOTAL COST SUMMARY Lodi Unified School District