Page 688 - Facilities Master Plan 2016
P. 688

Lodi Unified School District                                           Lodi Unified School District
          Maintenance & Operations Facility                                      Manlio Silva Growth K-8
          Facilities Master Plan - Total Program Cost                            Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16  Opinion of Probable Cost                                     19-Apr-16
                        Project Cost Summary (2016$) - Maintenance & Operations Facility          Project Cost Summary (2016$) - Manlio Silva Growth K-8
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          12 Safety, Security & Campus Control             $           3,302,000 $                 4,392,000  01 Modernize & Reconfigure Aging Classrooms  $                         -  $                             -
            12b Safety improvements to and/or new parent/bus drop-off areas and parking  Not included in this Facilities Needs Assessment
            12b.1 New Parking Lot            175,315 sf  $               16.00 $         2,805,000
            12b.11 New concrete walkways                8,750 sf  $               15.00 $            131,000
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000  02 Existing Building Systems & Toilets  $                         -  $                             -
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000  Not included in this Facilities Needs Assessment
            12h Fencing with controlled campus entrances
            12h.1 Chain Link Perimeter Fencing                2,250 lf  $               99.00 $            223,000
            12h.4 Rolling Chain Link Gate                        4 ea  $       25,200.00 $            101,000  03 Site Utilities  $                         -  $                             -
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           653,400 sf  $                 0.26
          13 District Support Facilities                   $         12,961,000 $              17,238,000  3b Updated sewer service lines           653,400 sf  $                 0.46
            13d M&O / Warehouse / Support Facilities                               3c Updated water service lines           653,400 sf  $                 0.63
            13d.1 Relocate Storage Containers                     14 ea  $       12,500.00 $            175,000  3d Updated electrical mains and distribution           653,400 sf  $                 0.81
            13d.2 New M&O / Warehouse / Support             33,735 sf  $             372.00 $      12,550,000  3e Updated storm drainage system           653,400 sf  $                 0.41
            13d.3 Sitework & Site Improvements             33,735 sf  $                 7.00 $            236,000
                                                                                 04 Classrooms New Construction                   $                         -  $                             -
          14 Outdoor Learning Environments & Quads         $                       -  $                             -
            Not included in this Facilities Needs Assessment                       4a New Construction - Pre-School, DK & Kindergarten
                                                                                    4a.2 New Pre-School, DK & Kindergarten Building             10,395 sf  $             395.00
           15 Exterior Play Spaces, Playfields & Hardcourts  $                       -  $                             -  4a.4 Sitework & Site Improvements             10,395 sf  $               38.00
            Not included in this Facilities Needs Assessment                       4b New Construction - Classrooms
                                                                                    4b.5 New Elementary Classroom Building (2-story)             43,411 sf  $             449.00
           16 Next Generation Classroom Flexibility (Furniture)  $                       -  $                             -
            Not included in this Facilities Needs Assessment                        4b.7 New Middle School Classroom Building (2-story)                7,661 sf  $             449.00
                                                                                    4b.10 Sitework & Site Improvements             25,536 sf  $               38.00
           17 Technology Infrastructure                    $                       -  $                             -
            Not included in this Facilities Needs Assessment                     05 Maker Spaces & Science Labs                   $                         -  $                             -
                                                                                   5a ES Science / Creativity Labs
                                                                                    5a.6 New ES Science / Creativity Labs Building                 2,640 sf  $             440.00
                                                                                    5a.7 Sitework & Site Improvements                2,640 sf  $               38.00
          Total Construction/Project Cost (2016$)          $         16,915,000  $22,497,000
                                                                                   5b MS / HS Science Labs
                                                                                    5b.1 New MS/HS  Science Labs Building                 3,168 sf  $             449.00
                                                                                    5b.2 Sitework & Site Improvements                3,168 sf  $               38.00
          The following items are excluded from this budget:
           Utility hook-up fees & City connection fees.
           Offsite work and traffic signals.
           Land acquisition costs.                                               06 Electives                                     $                         -  $                             -
                                                                                   6a MS/HS Electives
           Hazardous material surveys, abatement, and disposal.                     6a.6 New MS/HS Electives Building                 3,520 sf  $             413.00
           Escalation (Costs are in 2016$ calculated to the end of the year).
                                                                                    6a.7 Sitework & Site Improvements                3,520 sf  $               38.00
                                                                                 07 Performing Arts Improvements                  $                         -  $                             -
                                                                                   7a Music Lab
                                                                                    7a.4 New Music Lab                    2,624 sf  $             449.00
                                                                                    7a.5 Sitework & Site Improvements                2,624 sf  $               38.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  659