Lodi Unified School District                                            Lodi Unified School District
          Joe Serna Charter School                                                Joe Serna Charter School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                          Project Cost Summary (2016$) - Joe Serna Charter School                 Project Cost Summary (2016$) - Joe Serna Charter School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          01 Modernize & Reconfigure Aging Classrooms      $              761,000 $                 1,012,000  05 Maker Spaces & Science Labs  $                 67,000 $                      89,000
            1b Replacement or repair of walls                                      5a ES Science / Creativity Labs
            1b.2 Repair walls                     6,420 sf  $               12.60 $              81,000
            1c Replacement or repair of windows                                     5a.4 Modernize ES Science / Creativity Labs Building                    504 sf  $             132.00 $              67,000
            1c.1 Replace windows                  6,420 sf  $               18.00 $            116,000  5b MS / HS Science Labs
            1d Replacement or repair of doors (other than safety locks              5b.1 New MS/HS  Science Labs Building                 1,862 sf  $             484.92  2-story
            @ classroom doors)                                                      5b.2 Sitework & Site Improvements                   931 sf  $               38.00
            1d.1 Replace doors & hardware                6,420 sf  $               13.50 $              87,000
            1e Replacement or repair of floors
            1e.1 Replace floors                   6,420 sf  $               14.40 $              92,000  06 Electives             $                       -  $                             -
            1f Replacement or repair of ceilings                                   6a MS/HS Electives
            1f.1 Replace ceilings                 6,420 sf  $               27.00 $            173,000  6a.6 New MS/HS Electives Building                 1,862 sf  $             446.04  2-story
            1g Patch & Paint Interior/Exterior                                      6a.7 Sitework & Site Improvements                   931 sf  $               38.00
            1g.1 Patch & paint interior                6,420 sf  $                 3.10 $              20,000
            1g.2 Patch & paint exterior                6,420 sf  $                 4.50 $              29,000
            1I Exterior Façade Enhancement                3,200 sf  $               47.25 $            151,000  07 Performing Arts Improvements  $                       -  $                             -
            1o Replace Existing Roofing             24,046 sf  $               20.93  7a Music Lab
            1p Repair Existing Covered Walkways / Hallways                   960 sf  $               13.00 $              12,000  7a.4 New Music Lab                1,862 sf  $             484.92  2-story
                                                                                    7a.5 Sitework & Site Improvements                   931 sf  $               38.00
          02 Existing Building Systems & Toilets           $              735,000 $                    978,000
            2a HVAC system upgrades                6,420 sf  $               29.00 $            186,000  08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -
                                                                                   8a Elementary/Middle School multipurpose rooms
            2b Lighting upgrades - new interior lighting & controls                6,420 sf  $               15.00 $              96,000  8a.2 Modernize Multipurpose Room                6,372 sf  $               99.00
            2c Electrical upgrades                                                 8c Food service areas
            2c.1 Upgrade electrical wiring & increase electrical                    8c.2 Modernize Food Service                   660 sf  $             175.00
            outlets                               6,420 sf  $                 9.00 $              58,000  8c.6 New Trash Enclosure                        1 ea  $       45,000.00
            2d Plumbing system upgrades                6,420 sf  $               11.00 $              71,000
            2e Replace aging plumbing, upgrade and/or expand
            restroom facilities                                                   09 Physical Education Improvements              $                       -  $                             -
            2e.2 Reconfigure Existing Restroom                1,460 sf  $             222.00 $            324,000  9c PE/Fitness Labs
            2f Energy-efficient building systems and controls (EMS                  9c.3 Reconfigure PE/Fitness Labs                2,296 sf  $             243.00
            system, per sf of Bldg)                6,420 sf  $                 7.20
                                                                                  10 Administration & Staff Support               $                       -  $                             -
          03 Site Utilities                                $              112,000 $                    149,000  10a Expanded, reorganized or relocated administration
            (For entire campus and site)                                           spaces
            3a Updated gas service lines             82,764 sf  $                 0.30  10a.2 Modernize Administration                2,740 sf  $             118.00
            3b Updated sewer service lines             82,764 sf  $                 0.53  10b Staff Collaboration/Work Rooms
            3c Updated water service lines             82,764 sf  $                 0.68  10b.2 Modernize Staff Collaboration/Work Rooms                   674 sf  $             118.00
            3d Updated electrical mains and distribution             82,764 sf  $                 1.35 $            112,000  10b.4 New Staff Collaboration/Work Rooms                   702 sf  $             423.36  2-story
            3e Updated storm drainage system             82,764 sf  $                 0.45  10b.5 Sitework & Site Improvements                   351 sf  $               38.00
            3f Electrical Capacity Upgrades                        1 ls  $     161,000.00
                                                                                  11 Library & Student Support Services           $              237,000 $                    315,000
          04 Classrooms New Construction                   $                       -  $                             -  11a Elementary School Library/Innovation Lab
            4b New Construction - Classrooms                                        11a.3 Modernize Library/Innovation Lab Building                1,528 sf  $             122.00 $            186,000
            4b.1 Remove Portable Classrooms                        5 ea  $       11,000.00  11d Learning Center
            4b.3 Demolish Existing Buildings                1,800 sf  $               22.00  11d.3 Modernize Learning Center                   432 sf  $             119.00 $              51,000
            4b.5 New Elementary Classroom Building (2-story)                9,257 sf  $             449.00
            4b.10 Sitework & Site Improvements                4,628 sf  $               38.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming

         6.3       APPENDIX                                                                                                    Facilities Master Plan  656
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   680   681   682   683   684   685   686   687   688   689